A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2019, from the audited Statement of Development Expenditure.

Estimate 2019Anggaran
RM 2.00 bn
Spent 2019Sebenar
RM 0.00
0.0% of the estimate
Total cost of projectsKos Keseluruhan
RM 0.00
RMKe-11 spent to dateSebenar RMKe-11
RM 0.00
Totals as printed, JANM 2019, pp. 198–199

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00100Simpanan Luar JangkaRM 0.00RM 2,000,000,000.00RM 1,838,335,700.00
91.9%
RM 5,845,378,926.00JANM 2019, pp. 198–199
00200Simpanan Luar JangkaRM 0.00RM 0.00-RM 1,838,335,700.00-RM 5,845,378,926.00JANM 2019, pp. 198–199

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Development Expenditure (Lampiran 2).