A charged expenditure (T) vote: spending charged on the Consolidated Fund by law, not voted each year. What it was given and what it spent in 2019, by programme and activity, from the audited Statement of Operating Expenditure.

Original budgetAsal
RM 6.05 bn
RM 6,045,189,100.00
Revised budgetJumlah
RM 6.31 bn
RM 6,305,189,100.00
SpentSebenar
RM 6.12 bn
RM 6,116,274,617.54
97.0% of the revised budget
UnspentVarian
RM 188.91 m
RM 188,914,482.46
Totals as printed, JANM 2019, p. 70

By programme

Each programme's totals as the statement prints them. Open an activity below for every line to the sen.

CodeKodProgrammeProgramOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
010000Pemberian dan Serahan kepada Negeri-negeriRM 5,490,556,700.00RM 5,750,556,700.00RM 5,619,144,398.27
97.7%
RM 131,412,301.73JANM 2019, p. 69
020000Yuran dan SumbanganRM 125,632,400.00RM 130,239,903.00RM 128,756,245.68
98.9%
RM 1,483,657.32JANM 2019, p. 70
030000Bayaran PampasanRM 100,000,000.00RM 131,500,000.00RM 118,567,804.06
90.2%
RM 12,932,195.94JANM 2019, p. 70
040000Bayaran Balik, Bayaran Ganti dan PenebusanRM 329,000,000.00RM 292,892,497.00RM 249,806,169.53
85.3%
RM 43,086,327.47JANM 2019, p. 70

Every activity, line by line

Open an activity to see its spending categories exactly as printed, to the sen, each with the page it was read from.

The 2019 statement prints the original budget, the revised budget and actual spending only, with no supplementary or virement columns.

010000Pemberian dan Serahan kepada Negeri-negeri

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
010100Pemberian Mengikut Bilangan OrangRevised RM 410,070,480.00Spent RM 410,070,480.00
100.0%

Activity total as printed: revised RM 410,070,480.00, spent RM 410,070,480.00 (JANM 2019, p. 68).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 410,000,000.00RM 410,070,480.00RM 410,070,480.00
100.0%
RM 0.00JANM 2019, p. 68
010200Penyelenggaraan Jalan Raya Negeri Yang Mencapai Mutu MinimumRevised RM 3,410,537,043.00Spent RM 3,290,537,047.00
96.5%

Activity total as printed: revised RM 3,410,537,043.00, spent RM 3,290,537,047.00 (JANM 2019, p. 68).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 3,808,000,000.00RM 3,410,537,043.00RM 3,290,537,047.00
96.5%
RM 119,999,996.00JANM 2019, p. 68
010300Penyelenggaraan Jalan Raya Negeri Yang SubstandardRevised RM 1,286,686,188.00Spent RM 1,286,686,184.00
100.0%

Activity total as printed: revised RM 1,286,686,188.00, spent RM 1,286,686,184.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 900,000,000.00RM 1,286,686,188.00RM 1,286,686,184.00
100.0%
RM 4.00JANM 2019, p. 69
010400Penyelenggaraan Jalan Raya Negeri Jalan Sehala di Pulau Destinasi PelanconganRevised RM 537,597.00Spent RM 537,597.00
100.0%

Activity total as printed: revised RM 537,597.00, spent RM 537,597.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 400,000.00RM 537,597.00RM 537,597.00
100.0%
RM 0.00JANM 2019, p. 69
010500Pemberian Khas Tahunan SarawakRevised RM 16,000,000.00Spent RM 16,000,000.00
100.0%

Activity total as printed: revised RM 16,000,000.00, spent RM 16,000,000.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 16,000,000.00RM 16,000,000.00RM 16,000,000.00
100.0%
RM 0.00JANM 2019, p. 69
010600Pemberian Khas Tahunan SabahRevised RM 26,700,000.00Spent RM 26,700,000.00
100.0%

Activity total as printed: revised RM 26,700,000.00, spent RM 26,700,000.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 26,700,000.00RM 26,700,000.00RM 26,700,000.00
100.0%
RM 0.00JANM 2019, p. 69
010700Pemberian Pertambahan HasilRevised RM 250,000,000.00Spent RM 250,000,000.00
100.0%

Activity total as printed: revised RM 250,000,000.00, spent RM 250,000,000.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 0.00RM 250,000,000.00RM 250,000,000.00
100.0%
RM 0.00JANM 2019, p. 69
010800Pemberian Tahunan Kepada Pihak Berkuasa Tempatan (Geran Tahunan Berdasarkan Kaedah Keseimbangan)Revised RM 304,209,692.00Spent RM 302,797,452.27
99.5%

Activity total as printed: revised RM 304,209,692.00, spent RM 302,797,452.27 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 303,641,000.00RM 304,209,692.00RM 302,797,452.27
99.5%
RM 1,412,239.73JANM 2019, p. 69
010900Pemberian Tahunan SelangorRevised RM 25,805,700.00Spent RM 25,805,638.00
100.0%

Activity total as printed: revised RM 25,805,700.00, spent RM 25,805,638.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 25,805,700.00RM 25,805,700.00RM 25,805,638.00
100.0%
RM 62.00JANM 2019, p. 69
011000Pemberian Tahunan KedahRevised RM 20,010,000.00Spent RM 10,010,000.00
50.0%

Activity total as printed: revised RM 20,010,000.00, spent RM 10,010,000.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 10,000.00RM 20,010,000.00RM 10,010,000.00
50.0%
RM 10,000,000.00JANM 2019, p. 69

020000Yuran dan Sumbangan

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
020100Yuran Tambahan Kepada Persatuan Pembangunan AntarabangsaRevised RM 24,369,636.00Spent RM 23,879,492.00
98.0%

Activity total as printed: revised RM 24,369,636.00, spent RM 23,879,492.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 23,000,000.00RM 24,369,636.00RM 23,879,492.00
98.0%
RM 490,144.00JANM 2019, p. 69
020200Penebusan Treasury Notes Yang Dikeluarkan Kepada Bank Antarabangsa Untuk Pemulihan dan Pembangunan Untuk YuranRevised RM 100.00Spent RM 0.00
0.0%

Activity total as printed: revised RM 100.00, spent RM 0.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100.00RM 100.00RM 0.00
0.0%
RM 100.00JANM 2019, p. 69
020300Penebusan Treasury Notes Yang Dikeluarkan Kepada Asian Development FundRevised RM 7,239,839.00Spent RM 7,197,611.20
99.4%

Activity total as printed: revised RM 7,239,839.00, spent RM 7,197,611.20 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 7,000,000.00RM 7,239,839.00RM 7,197,611.20
99.4%
RM 42,227.80JANM 2019, p. 69
020400Yuran Tambahan Kepada Perbadanan Kewangan AntarabangsaRevised RM 100.00Spent RM 0.00
0.0%

Activity total as printed: revised RM 100.00, spent RM 0.00 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100.00RM 100.00RM 0.00
0.0%
RM 100.00JANM 2019, p. 69
020500Sumbangan Kepada Bank Pembangunan IslamRevised RM 19,719,311.00Spent RM 19,712,160.36
100.0%

Activity total as printed: revised RM 19,719,311.00, spent RM 19,712,160.36 (JANM 2019, p. 69).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 19,000,000.00RM 19,719,311.00RM 19,712,160.36
100.0%
RM 7,150.64JANM 2019, p. 69
020600Yuran Tambahan Kepada Bank Pembangunan AsiaRevised RM 51,632,554.00Spent RM 51,632,553.04
100.0%

Activity total as printed: revised RM 51,632,554.00, spent RM 51,632,553.04 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 51,632,000.00RM 51,632,554.00RM 51,632,553.04
100.0%
RM 0.96JANM 2019, p. 70
020700Sumbangan Kepada International Fund for Agricultural DevelopmentRevised RM 100.00Spent RM 0.00
0.0%

Activity total as printed: revised RM 100.00, spent RM 0.00 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100.00RM 100.00RM 0.00
0.0%
RM 100.00JANM 2019, p. 70
020800Modal Caruman Kepada Multilateral Investment Guarantee Agency (MIGA)Revised RM 100.00Spent RM 0.00
0.0%

Activity total as printed: revised RM 100.00, spent RM 0.00 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100.00RM 100.00RM 0.00
0.0%
RM 100.00JANM 2019, p. 70
020900Caruman Saham Asian Infrastructure Investment Bank (AIIB)Revised RM 19,272,000.00Spent RM 18,489,294.00
95.9%

Activity total as printed: revised RM 19,272,000.00, spent RM 18,489,294.00 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 17,500,000.00RM 19,272,000.00RM 18,489,294.00
95.9%
RM 782,706.00JANM 2019, p. 70
021000Yuran Tambahan Saham Islamic Corporation for the Development of the Private Sector (ICD) KeduaRevised RM 8,006,163.00Spent RM 7,845,135.08
98.0%

Activity total as printed: revised RM 8,006,163.00, spent RM 7,845,135.08 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 7,500,000.00RM 8,006,163.00RM 7,845,135.08
98.0%
RM 161,027.92JANM 2019, p. 70

030000Bayaran Pampasan

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
030100Bayaran Tuntutan dan Pampasan Atas Perintah MahkamahRevised RM 131,500,000.00Spent RM 118,567,804.06
90.2%

Activity total as printed: revised RM 131,500,000.00, spent RM 118,567,804.06 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
20000Supplies and ServicesPerkhidmatan dan BekalanRM 0.00RM 5,000,000.00RM 377,258.73
7.5%
RM 4,622,741.27JANM 2019, p. 70
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100,000,000.00RM 126,500,000.00RM 118,190,545.33
93.4%
RM 8,309,454.67JANM 2019, p. 70

040000Bayaran Balik, Bayaran Ganti dan Penebusan

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
040100Bayaran Balik Cukai KastamRevised RM 278,732,497.00Spent RM 236,154,353.26
84.7%

Activity total as printed: revised RM 278,732,497.00, spent RM 236,154,353.26 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 320,000,000.00RM 278,732,497.00RM 236,154,353.26
84.7%
RM 42,578,143.74JANM 2019, p. 70
040200Bayaran Balik Wang Lesen, Lencana dan Plat Kereta SewaRevised RM 8,160,000.00Spent RM 7,737,018.23
94.8%

Activity total as printed: revised RM 8,160,000.00, spent RM 7,737,018.23 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 5,000,000.00RM 8,160,000.00RM 7,737,018.23
94.8%
RM 422,981.77JANM 2019, p. 70
040300Bayaran Balik Wang Tak Dituntut Dari HasilRevised RM 6,000,000.00Spent RM 5,914,798.04
98.6%

Activity total as printed: revised RM 6,000,000.00, spent RM 5,914,798.04 (JANM 2019, p. 70).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 4,000,000.00RM 6,000,000.00RM 5,914,798.04
98.6%
RM 85,201.96JANM 2019, p. 70

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Operating Expenditure (Lampiran 1). % used and unspent are worked out from the printed columns.