Jabatan Perdana Menteri
A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2021, from the audited Statement of Development Expenditure.
Estimate 2021Anggaran
RM 5.91 bn
Spent 2021Sebenar
RM 5.89 bn
99.6% of the estimate; RM 1.62 m loan-funded
Total cost of projectsKos Keseluruhan
RM 140.15 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2021Anggaran | Spent 2021Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Kajian-kajian Kemungkinan | RM 243,021,135.00 | RM 27,820,701.00 | RM 26,846,110.40 | 96.5% | RM 26,846,110.40 | JANM 2021, pp. 190–191 |
| 00101 | Majlis Keselamatan Negara | RM 1,771,852,000.00 | RM 285,671,397.00 | RM 283,561,655.02 | 99.3% | RM 283,561,655.02 | JANM 2021, pp. 190–191 |
| 00102 | Projek Kemiskinan Semenanjung/Sabah/Sarawak | RM 530,000,000.00 | RM 3,000,000.00 | RM 3,000,000.00 | 100.0% | RM 3,000,000.00 | JANM 2021, pp. 190–191 |
| 00104 | Penyusunan Semula Masyarakat | RM 5,750,000,000.00 | RM 100.00 | RM 0.00 | 0.0% | RM 0.00 | JANM 2021, pp. 190–191 |
| 00107 | Southern Johor Development | RM 1,571,340,000.00 | RM 44,750,000.00 | RM 44,750,000.00 | 100.0% | RM 44,750,000.00 | JANM 2021, pp. 190–191 |
| 00108 | Program Pembangunan | RM 46,199,176,383.00 | RM 669,355,197.00 | RM 669,016,883.24 | 100.0% | RM 669,016,883.24 | JANM 2021, pp. 190–191 |
| 00109 | Program Serantau IMT | RM 25,000,000.00 | RM 5,000,000.00 | RM 4,020,841.00 | 80.4% | RM 4,020,841.00 | JANM 2021, pp. 190–191 |
| 00113 | Pembangunan Lima Koridor | RM 14,089,656,205.00 | RM 659,940,553.00 | RM 659,940,427.65 | 100.0% | RM 659,940,427.65 | JANM 2021, pp. 190–191 |
| 00114 | Projek Pembangunan Langkawi | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 00117 | Pembangunan Perkampungan Nelayan di Lumut dan Pulau Pangkor, Perak | RM 123,571,355.00 | RM 4,200,300.00 | RM 4,200,000.00 | 100.0% | RM 4,200,000.00 | JANM 2021, pp. 190–191 |
| 00121 | Infrastruktur Luar Bandar | RM 825,000,000.00 | RM 62,350,000.00 | RM 62,350,000.00 | 100.0% | RM 62,350,000.00 | JANM 2021, pp. 190–191 |
| 00125 | Projek Public Private Partnership (PPP) | RM 4,067,853,800.00 | RM 838,267,100.00 | RM 833,667,385.74 | 99.5% | RM 833,667,385.74 | JANM 2021, pp. 190–191 |
| 00201 | Program Pembangunan Sosioekonomi Masyarakat India | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 00210 | Perumahan Penjawat Awam 1Malaysia | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 00300 | Institut Latihan Statistik | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 00400 | Pengkomputeran Jabatan Peguam NegaraNote: P.06 – Butiran 00400, 12200 dan 81000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 36,808,828.00 | RM 389,798.00 | RM 389,787.00 | 100.0% | RM 389,787.00 | JANM 2021, pp. 190–191 |
| 00401 | Pembangunan Jabatan Peguam Negara | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 00600 | Kemajuan Guna Tenaga Manusia | RM 31,000,000.00 | RM 1,002,060.00 | RM 936,436.73 | 93.5% | RM 936,436.73 | JANM 2021, pp. 190–191 |
| 00900 | Bantuan Teknik dan Perunding | RM 80,000,000.00 | RM 3,785,000.00 | RM 3,687,494.40 | 97.4% | RM 3,687,494.40 | JANM 2021, pp. 190–191 |
| 01100 | Jabatan Kemajuan Orang Asli (JAKOA) | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 02700 | Menaik Taraf Masjid Wilayah Persekutuan Kuala Lumpur | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 03400 | Kompleks Latihan Islam/Tahfiz/Pusat Komuniti Orang Asli | RM 34,720,000.00 | RM 3,235,600.00 | RM 3,221,544.29 | 99.6% | RM 3,221,544.29 | JANM 2021, pp. 190–191 |
| 03600 | Membina dan Menaik Taraf Pagar Keselamatan dan Lain-lain | RM 25,000,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 04000 | Penyertaan Bumiputra Pulau Pinang | RM 150,000,000.00 | RM 20,200,000.00 | RM 20,193,784.85 | 100.0% | RM 20,193,784.85 | JANM 2021, pp. 190–191 |
| 04801 | Pembinaan Masjid/Surau dan Pembaikan/Naik Taraf | RM 326,220,000.00 | RM 11,866,547.00 | RM 11,603,149.70 | 97.8% | RM 11,603,149.70 | JANM 2021, pp. 190–191 |
| 04802 | Pembinaan Sekolah Agama | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 06000 | Studio MEPS/Pusat Penyelidikan Halal/Kajian | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 06100 | Development of Halal Industry | RM 10,982,000.00 | RM 3,519,853.00 | RM 3,519,549.45 | 100.0% | RM 3,519,549.45 | JANM 2021, pp. 190–191 |
| 06900 | Membina Pejabat dan Perumahan SPRM | RM 101,772,500.00 | RM 9,073,900.00 | RM 9,073,832.48 | 100.0% | RM 9,073,832.48 | JANM 2021, pp. 190–191 |
| 09000 | Bangunan-bangunan Mahkamah/Kajian-kajian di bawah BHEUU | RM 1,062,583,000.00 | RM 43,348,179.00 | RM 43,244,509.26 | 99.8% | RM 43,244,509.26 | JANM 2021, pp. 190–191 |
| 09400 | Pengkomputeran Mahkamah | RM 231,164,325.00 | RM 90,576,245.00 | RM 90,575,965.40 | 100.0% | RM 90,575,965.40 | JANM 2021, pp. 190–191 |
| 09900 | Pembangunan Suruhanjaya Pilihan Raya (SPR) | RM 30,000,000.00 | RM 7,890,950.00 | RM 7,882,253.18 | 99.9% | RM 7,882,253.18 | JANM 2021, pp. 190–191 |
| 09910 | Agensi Pengurusan Bencana Negara (NADMA) | RM 116,555,000.00 | RM 7,853,717.00 | RM 7,853,549.20 | 100.0% | RM 7,853,549.20 | JANM 2021, pp. 190–191 |
| 10200 | Perolehan Komputer | RM 216,827,499.00 | RM 31,942,454.00 | RM 30,975,726.64 | 97.0% | RM 30,975,726.64 | JANM 2021, pp. 190–191 |
| 10500 | Projek Pusara Negara | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 10600 | Perolehan Kerajaan Elektronik | RM 7,298,242,789.00 | RM 688,764,300.00 | RM 688,530,695.36 | 100.0% | RM 688,530,695.36 | JANM 2021, pp. 190–191 |
| 11100 | Pengurusan Kuarters Kerajaan/Rumah Rasmi | RM 1,746,500,000.00 | RM 203,228,746.00 | RM 198,936,863.52 | 97.9% | RM 198,936,863.52 | JANM 2021, pp. 190–191 |
| 11300 | Bangunan Gunasama Persekutuan Sarawak/Rumah Kediaman SUP Sarawak | RM 170,000,000.00 | RM 100.00 | RM 0.00 | 0.0% | RM 0.00 | JANM 2021, pp. 190–191 |
| 11800 | Pembangunan Mahkamah Syariah | RM 195,117,000.00 | RM 28,880,642.00 | RM 27,574,466.89 | 95.5% | RM 27,574,466.89 | JANM 2021, pp. 190–191 |
| 12200 | Pembinaan Institut Latihan Jabatan Audit NegaraNote: P.06 – Butiran 00400, 12200 dan 81000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 39,575,000.00 | RM 10,422,010.00 | RM 10,385,410.37 | 99.7% | RM 10,385,410.37 | JANM 2021, pp. 190–191 |
| 15000 | Pengubahsuaian dan Menaik Taraf Parlimen Malaysia | RM 365,100,000.00 | RM 6,781,800.00 | RM 6,781,753.71 | 100.0% | RM 6,781,753.71 | JANM 2021, pp. 190–191 |
| 16000 | Jabatan Pertahanan Awam Malaysia (JPAM) | RM 205,000,000.00 | RM 18,930,100.00 | RM 18,588,742.99 | 98.2% | RM 18,588,742.99 | JANM 2021, pp. 190–191 |
| 16200 | Projek Jalan Felda | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 16300 | Projek Sistem Bekalan Air Felda | RM 448,516,671.00 | RM 25,499,800.00 | RM 25,499,750.00 | 100.0% | RM 25,499,750.00 | JANM 2021, pp. 190–191 |
| 16500 | Projek Kelestarian Felda | RM 5,000,000,000.00 | RM 200,000,000.00 | RM 200,000,000.00 | 100.0% | RM 200,000,000.00 | JANM 2021, pp. 190–191 |
| 17200 | Pusat Aktiviti Perpaduan | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 17300 | Pusat Rukun Tetangga | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 17700 | Pembinaan Istana Negara di Jalan Duta | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 17800 | Membaiki dan Menaiktaraf Istana Melawati | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 50000 | Pembangunan Harta Wakaf | RM 78,696,007.00 | RM 5,458,500.00 | RM 5,458,338.48 | 100.0% | RM 5,458,338.48 | JANM 2021, pp. 190–191 |
| 69000 | Unit Peneraju | RM 1,793,800,300.00 | RM 118,800,000.00 | RM 118,800,000.00 | 100.0% | RM 118,800,000.00 | JANM 2021, pp. 190–191 |
| 70101 | Perbadanan Kemajuan Negeri: Johor | RM 194,123,500.00 | RM 14,316,600.00 | RM 14,316,475.00 | 100.0% | RM 14,316,475.00 | JANM 2021, pp. 190–191 |
| 70102 | Perbadanan Kemajuan Negeri: Kedah | RM 289,123,692.90 | RM 16,466,799.00 | RM 16,466,698.57 | 100.0% | RM 16,466,698.57 | JANM 2021, pp. 190–191 |
| 70103 | Perbadanan Kemajuan Negeri: Kelantan | RM 116,110,060.00 | RM 4,230,200.00 | RM 4,230,000.00 | 100.0% | RM 4,230,000.00 | JANM 2021, pp. 190–191 |
| 70104 | Perbadanan Kemajuan Negeri: Melaka | RM 22,723,207.00 | RM 200.00 | RM 0.00 | 0.0% | RM 0.00 | JANM 2021, pp. 190–191 |
| 70106 | Perbadanan Kemajuan Negeri: Pahang | RM 4,600,000.00 | RM 1,500,000.00 | RM 1,500,000.00 | 100.0% | RM 1,500,000.00 | JANM 2021, pp. 190–191 |
| 70109 | Perbadanan Kemajuan Negeri: Perlis | RM 6,140,000.00 | RM 710,100.00 | RM 710,000.00 | 100.0% | RM 710,000.00 | JANM 2021, pp. 190–191 |
| 70111 | Perbadanan Kemajuan Negeri: Terengganu | RM 42,283,816.10 | RM 7,254,576.00 | RM 7,254,476.00 | 100.0% | RM 7,254,476.00 | JANM 2021, pp. 190–191 |
| 70112 | Perbadanan Kemajuan Negeri: Sabah | RM 51,278,114.00 | RM 6,885,400.00 | RM 6,885,300.00 | 100.0% | RM 6,885,300.00 | JANM 2021, pp. 190–191 |
| 70113 | Perbadanan Kemajuan Negeri: Sarawak | RM 11,430,125.14 | RM 3,510,724.00 | RM 3,510,524.00 | 100.0% | RM 3,510,524.00 | JANM 2021, pp. 190–191 |
| 71000 | Penyelarasan Program Pembasmian Kemiskinan | RM 480,251,630.00 | RM 54,346,939.00 | RM 54,110,340.11 | 99.6% | RM 54,110,340.11 | JANM 2021, pp. 190–191 |
| 74000 | Sumbangan untuk NGO dan Rumah Ibadat Masyarakat India | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 80500 | Program Komunikasi Dasar | RM 10,000,000.00 | RM 100.00 | RM 0.00 | 0.0% | RM 0.00 | JANM 2021, pp. 190–191 |
| 81000 | Kajian Kemungkinan UKASNote: P.06 – Butiran 00400, 12200 dan 81000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 2,653,308.42 | RM 498,111.00 | RM 498,100.35 | 100.0% | RM 498,100.35 | JANM 2021, pp. 190–191 |
| 83000 | Malaysian Industry Government Group for High Technology (MIGHT) | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 92000 | Agensi Inovasi Malaysia | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 190–191 | |
| 93000 | Projek-projek KecilNote: P.06 – Butiran 93000 dan 96300 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 4,600,000,000.00 | RM 600,000,010.00 | RM 599,998,334.56 | 100.0% | RM 599,998,334.56 | JANM 2021, pp. 192–193 |
| 93500 | Projek Khas | RM 4,400,000,000.00 | RM 266,370,641.00 | RM 264,695,111.45 | 99.4% | RM 264,695,111.45 | JANM 2021, pp. 192–193 |
| 93600 | Projek Mesra Rakyat | RM 1,665,000,000.00 | RM 333,000,000.00 | RM 332,999,355.33 | 100.0% | RM 332,999,355.33 | JANM 2021, pp. 192–193 |
| 93900 | Kerja-kerja Naiktaraf Jalan | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 192–193 | |
| 94000 | Perkhidmatan Kerajaan Digital | RM 1,106,808,200.00 | RM 20,498,750.00 | RM 20,446,809.64 | 99.8% | RM 20,446,809.64 | JANM 2021, pp. 192–193 |
| 96000 | Pengurusan Aset dan Bangunan Jabatan Perdana Menteri | RM 1,598,283,140.31 | RM 225,287,772.00 | RM 224,894,769.86 | 99.8% | RM 224,894,769.86 | JANM 2021, pp. 192–193 |
| 96100 | Perolehan dan Bayaran Tanah JPM | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 192–193 | |
| 96300 | Kajian-Kajian dibawah JPMNote: P.06 – Butiran 93000 dan 96300 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 5,000,000.00 | RM 4,500,010.00 | RM 4,500,000.00 | 100.0% | RM 4,500,000.00 | JANM 2021, pp. 192–193 |
| 97000 | Dana Fasilitasi | RM 29,996,000,000.00 | RM 82,788,299.00 | RM 82,788,299.00 | 100.0% | RM 82,788,299.00 | JANM 2021, pp. 192–193 |
| 98000 | Malaysia Nuclear Energy | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 192–193 | |
| 99000 | Banci Ekonomi/EKS | RM 561,738,450.00 | RM 129,996,320.00 | RM 125,329,133.05 | 96.4% | RM 125,329,133.05 | JANM 2021, pp. 192–193 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2021, Statement of Development Expenditure (Lampiran 2).