Estimate 2022Anggaran
RM 142.56 m
Spent 2022Sebenar
RM 140.51 m
98.6% of the estimate
Total cost of projectsKos Keseluruhan
RM 751.26 m
RMKe-12 spent to dateSebenar RMKe-12
RM 209.35 m
Totals as printed, JANM 2022, pp. 188–189

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00201Program Pembangunan Sosioekonomi Masyarakat IndiaRM 268,529,479.00RM 63,072,100.00RM 62,815,564.64
99.6%
RM 128,602,930.21JANM 2022, pp. 188–189
17200Pusat Aktiviti PerpaduanRM 52,950,000.00RM 3,396,000.00RM 3,225,142.08
95.0%
RM 5,870,687.06JANM 2022, pp. 188–189
17300Pusat Rukun TetanggaRM 6,180,000.00RM 2,054,000.00RM 1,944,735.20
94.7%
RM 2,356,459.14JANM 2022, pp. 188–189
17400Program Pembangunan Kampung BaruNote: P.14 – Butiran 17400 - Peruntukan sebanyak RM84,000,000 akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluanRM 423,600,000.00RM 74,037,400.00RM 72,521,375.64
98.0%
RM 72,521,375.64JANM 2022, pp. 188–189

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2022, Statement of Development Expenditure (Lampiran 2).