Kementerian Luar Negeri
A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2025, from the audited Statement of Development Expenditure.
Estimate 2025Anggaran
RM 157.96 m
Spent 2025Sebenar
RM 155.24 m
98.3% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.34 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2025Anggaran | Spent 2025Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Pejabat-pejabat dan Bangunan-bangunan di Seberang Laut | RM 1,099,206,515.00 | RM 100,662,700.00 | RM 99,414,384.05 | 98.8% | RM 330,960,472.30 | JANM 2025, pp. 202–203 |
| 00200 | Alat-alat Kelengkapan Komunikasi | RM 5,750,000.00 | RM 0.00 | RM 0.00 | RM 4,164,690.12 | JANM 2025, pp. 202–203 | |
| 00400 | Tanah dan Kerja Awalan | RM 5,000,000.00 | RM 900,000.00 | RM 797,819.51 | 88.7% | RM 2,200,993.32 | JANM 2025, pp. 202–203 |
| 00500 | Program MTCP | RM 60,000,000.00 | RM 20,000,000.00 | RM 18,632,686.28 | 93.2% | RM 49,182,019.17 | JANM 2025, pp. 202–203 |
| 00700 | PPP/PFI | RM 167,001,500.00 | RM 36,396,500.00 | RM 36,391,480.16 | 100.0% | RM 105,005,017.25 | JANM 2025, pp. 202–203 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).