Skip to content

Kementerian Kesihatan

A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2025, from the audited Statement of Development Expenditure.

Estimate 2025Anggaran
RM 6.20 bn
Spent 2025Sebenar
RM 5.96 bn
96.2% of the estimate
Total cost of projectsKos Keseluruhan
RM 64.88 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 29.35 bn
Totals as printed, JANM 2025, pp. 222–223

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00101Pembinaan Kolej BaharuRM 65,737,223.00RM 0.00RM 0.00RM 258,854.34JANM 2025, pp. 222–223
00102Naik Taraf Projek LatihanRM 58,170,886.00RM 11,504,346.00RM 11,167,881.79
97.1%
RM 26,187,031.47JANM 2025, pp. 222–223
00105Latihan dalam PerkhidmatanRM 229,361,753.00RM 58,171,000.00RM 57,819,584.61
99.4%
RM 181,322,343.09JANM 2025, pp. 222–223
00201Perkhidmatan Kesihatan Luar BandarRM 3,673,042,204.00RM 255,313,479.00RM 227,764,006.40
89.2%
RM 742,168,483.57JANM 2025, pp. 222–223
00202BAKASRM 54,416,600.00RM 8,399,400.00RM 7,941,577.74
94.5%
RM 49,153,754.10JANM 2025, pp. 222–223
00203Perkhidmatan Kesihatan BandarRM 3,381,657,095.00RM 205,240,006.00RM 194,199,549.73
94.6%
RM 1,042,196,733.77JANM 2025, pp. 222–223
00204Klinik BergerakRM 15,750,000.00RM 4,709,500.00RM 449,999.70
9.6%
RM 2,146,853.65JANM 2025, pp. 222–223
00300Kemudahan HospitalRM 23,236,043,962.00RM 641,303,000.00RM 636,332,009.69
99.2%
RM 7,447,406,241.92JANM 2025, pp. 222–223
00400Hospital BaharuRM 6,217,808,053.00RM 598,981,293.00RM 586,455,521.07
97.9%
RM 2,250,633,169.65JANM 2025, pp. 222–223
00500Penyelidikan dan Pembangunan (R&D)RM 247,621,664.00RM 39,481,901.00RM 34,426,016.34
87.2%
RM 130,295,604.60JANM 2025, pp. 222–223
00600Ubahsuai, Naik Taraf dan PembaikanRM 1,334,000,000.00RM 391,296,024.00RM 373,015,912.39
95.3%
RM 1,280,268,601.42JANM 2025, pp. 222–223
00700Perolehan dan Penyelenggaraan TanahRM 205,561,500.00RM 67,785,140.00RM 64,979,763.06
95.9%
RM 142,636,580.55JANM 2025, pp. 222–223
00800Kemudahan Teknologi Maklumat dan Komunikasi (ICT)RM 1,245,791,075.00RM 105,120,961.00RM 93,265,503.55
88.7%
RM 388,280,853.64JANM 2025, pp. 222–223
00900Penyelenggaraan Kuarters KKMRM 127,140,000.00RM 35,000,000.00RM 30,754,372.21
87.9%
RM 109,163,309.89JANM 2025, pp. 222–223
00901Kemudahan Kuarters Luar BandarRM 85,388,905.00RM 8,310,496.00RM 4,822,154.29
58.0%
RM 44,367,692.26JANM 2025, pp. 222–223
00902Kemudahan Kuarters BandarRM 316,066,585.00RM 32,260,798.00RM 28,813,990.65
89.3%
RM 187,441,094.20JANM 2025, pp. 222–223
00904Pejabat dan Jabatan KesihatanRM 343,623,922.00RM 1,752,624.00RM 1,632,849.60
93.2%
RM 100,895,581.74JANM 2025, pp. 222–223
01100Peralatan dan KenderaanRM 10,222,065,591.00RM 619,094,149.00RM 576,047,568.14
93.0%
RM 6,749,220,959.06JANM 2025, pp. 222–223
01200PPP/PFIRM 13,747,318,691.00RM 3,111,841,383.00RM 3,029,598,745.52
97.4%
RM 8,467,134,550.35JANM 2025, pp. 222–223
09000Pelbagai Suntikan ModalRM 69,000,000.00RM 1,000,000.00RM 1,000,000.00
100.0%
RM 8,750,000.00JANM 2025, pp. 222–223

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).