Kementerian Tenaga, Teknologi Hijau dan Air
A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2017, from the audited Statement of Development Expenditure.
Estimate 2017Anggaran
RM 1.58 bn
Spent 2017Sebenar
RM 1.52 bn
96.6% of the estimate; RM 499.31 m loan-funded
Total cost of projectsKos Keseluruhan
RM 26.74 bn
By group
The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.
| Group | Estimate 2017Anggaran | Spent 2017Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|
| Teknologi Hijau | RM 7.46 m | RM 7.41 m | 99.3% | RM 16.35 m | JANM 2017, pp. 226–227 |
| Tenaga | RM 401.37 m | RM 398.90 m | 99.4% | RM 661.48 m | JANM 2017, pp. 226–227 |
| Bekalan Air | RM 396.67 m | RM 390.60 m | 98.5% | RM 1.18 bn | JANM 2017, pp. 226–227 |
| Perkhidmatan Pembetungan | RM 769.69 m | RM 725.27 m | 94.2% | RM 1.52 bn | JANM 2017, pp. 226–227 |
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
Teknologi Hijau1 projectEstimate RM 7.46 m · Spent RM 7.41 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2017Anggaran | Spent 2017Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00107 | Projek Teknologi Hijau | RM 23,455,000.00 | RM 7,465,000.00 | RM 7,410,799.14 | 99.3% | RM 16,345,351.13 | JANM 2017, pp. 226–227 |
Tenaga4 projectsEstimate RM 401.37 m · Spent RM 398.90 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2017Anggaran | Spent 2017Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Program Kecekapan Tenaga dan Tenaga Diperbaharui | RM 172,143,700.00 | RM 31,190,000.00 | RM 30,745,821.84 | 98.6% | RM 45,574,564.94 | JANM 2017, pp. 226–227 |
| 03200 | Sabah Electricity Sdn. Bhd. (SESB)Note: P.29– Butiran 03200, 03203 dan 80000 - Peruntukan sebanyak RM 56,000,000 , RM 10 dan RM 189,000,000 bagi setiap butiran akan dibentangkan dalam Sesi Parlimen 2018 telah dimasuk kira sebagai pendahuluan. | RM 2,803,742,397.00 | RM 310,669,900.00 | RM 309,150,195.32 | 99.5% | RM 546,901,180.54 | JANM 2017, pp. 226–227 |
| 03202 | Penghantaran dan Pembahagian (Tenaga) | RM 123,576,500.00 | RM 30,506,000.00 | RM 30,506,000.00 | 100.0% | RM 40,506,000.00 | JANM 2017, pp. 226–227 |
| 03203 | Astana EkspoNote: P.29– Butiran 03200, 03203 dan 80000 - Peruntukan sebanyak RM 56,000,000 , RM 10 dan RM 189,000,000 bagi setiap butiran akan dibentangkan dalam Sesi Parlimen 2018 telah dimasuk kira sebagai pendahuluan. | RM 30,000,000.00 | RM 29,000,010.00 | RM 28,495,000.00 | 98.3% | RM 28,495,000.00 | JANM 2017, pp. 226–227 |
Bekalan Air14 projectsEstimate RM 396.67 m · Spent RM 390.60 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2017Anggaran | Spent 2017Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 06400 | Rancangan Bekalan Air Negeri Johor | RM 942,600,000.00 | RM 32,795,000.00 | RM 32,697,530.21 | 99.7% | RM 100,853,015.89 | JANM 2017, pp. 226–227 |
| 06500 | Rancangan Bekalan Air Negeri Kedah | RM 699,585,000.00 | RM 33,055,750.00 | RM 33,055,486.06 | 100.0% | RM 116,330,161.06 | JANM 2017, pp. 226–227 |
| 07000 | Rancangan Bekalan Air Negeri Kelantan | RM 263,600,000.00 | RM 23,025,800.00 | RM 22,730,439.65 | 98.7% | RM 51,902,355.65 | JANM 2017, pp. 226–227 |
| 07400 | Rancangan Bekalan Air Negeri Melaka | RM 164,000,000.00 | RM 25,060,000.00 | RM 24,966,924.46 | 99.6% | RM 54,946,081.78 | JANM 2017, pp. 226–227 |
| 07800 | Rancangan Bekalan Air Negeri Sembilan | RM 531,338,800.00 | RM 715,350.00 | RM 683,260.93 | 95.5% | RM 14,986,733.89 | JANM 2017, pp. 226–227 |
| 08100 | Rancangan Bekalan Air Negeri Pahang | RM 702,315,037.00 | RM 40,631,250.00 | RM 40,124,286.00 | 98.8% | RM 104,365,089.97 | JANM 2017, pp. 226–227 |
| 09100 | Rancangan Bekalan Air Negeri Selangor | RM 465,797,981.00 | RM 36,380,000.00 | RM 36,342,890.00 | 99.9% | RM 152,865,738.50 | JANM 2017, pp. 226–227 |
| 09400 | Rancangan Bekalan Air Negeri Terengganu | RM 5,000,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2017, pp. 226–227 | |
| 10300 | Rancangan Bekalan Air Pulau Pinang | RM 1,232,700,000.00 | RM 54,200,000.00 | RM 54,200,000.00 | 100.0% | RM 148,832,121.98 | JANM 2017, pp. 226–227 |
| 10900 | Rancangan Bekalan Air Negeri Perlis | RM 42,712,390.00 | RM 0.00 | RM 0.00 | RM 4,100,000.00 | JANM 2017, pp. 226–227 | |
| 11200 | Penyaluran Air antara Negeri | RM 3,935,575,000.00 | RM 11,444,950.00 | RM 11,444,945.15 | 100.0% | RM 105,725,602.79 | JANM 2017, pp. 226–227 |
| 11300 | Rancangan Bekalan Air Labuan | RM 202,750,159.00 | RM 11,896,050.00 | RM 11,521,735.78 | 96.8% | RM 39,809,207.08 | JANM 2017, pp. 226–227 |
| 11400 | Rancangan Bekalan Air Negeri Sabah | RM 2,078,382,133.00 | RM 72,056,500.00 | RM 71,889,391.91 | 99.8% | RM 145,869,043.24 | JANM 2017, pp. 226–227 |
| 11600 | Rancangan Bekalan Air Negeri Sarawak | RM 2,176,063,634.00 | RM 55,412,000.00 | RM 50,942,559.00 | 91.9% | RM 135,386,209.00 | JANM 2017, pp. 226–227 |
Perkhidmatan Pembetungan5 projectsEstimate RM 769.69 m · Spent RM 725.27 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2017Anggaran | Spent 2017Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 06000 | Sistem Pengurusan Maklumat KETTHA | RM 9,541,484.00 | RM 225,000.00 | RM 188,750.00 | 83.9% | RM 1,013,758.00 | JANM 2017, pp. 226–227 |
| 80000 | Projek Pembetungan NegaraNote: P.29– Butiran 03200, 03203 dan 80000 - Peruntukan sebanyak RM 56,000,000 , RM 10 dan RM 189,000,000 bagi setiap butiran akan dibentangkan dalam Sesi Parlimen 2018 telah dimasuk kira sebagai pendahuluan. | RM 9,569,320,032.26 | RM 768,201,150.00 | RM 723,876,271.01 | 94.2% | RM 1,504,639,773.27 | JANM 2017, pp. 226–227 |
| 80004 | Program Pembangunan Latihan Dan Kemahiran | RM 4,650,000.00 | RM 0.00 | RM 0.00 | RM 4,650,000.00 | JANM 2017, pp. 226–227 | |
| 80005 | Kerja-Kerja Sambungan Tanah | RM 56,150,000.00 | RM 0.00 | RM 0.00 | RM 8,492,075.83 | JANM 2017, pp. 226–227 | |
| 95000 | NRW Nasional | RM 510,000,000.00 | RM 1,260,000.00 | RM 1,209,197.66 | 96.0% | RM 1,209,197.66 | JANM 2017, pp. 226–227 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2017, Statement of Development Expenditure (Lampiran 2).