Development expenditure · 2017
Development spending 2017
Spending on projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020), by development (P) vote. From the audited Statement of Development Expenditure (Perbelanjaan Pembangunan, Lampiran 2). How these numbers are checked.
Estimate 2017Anggaran
RM 47.32 bn
Spent 2017Sebenar
RM 44.88 bn
% usedPrestasi
94.8%
of the estimate
RMKe-11 spent to dateSebenar RMKe-11
RM 86.88 bn
Totals as printed (Jumlah Perbelanjaan Pembangunan), JANM 2017, pp. 238–239. RM 2.61 bn of the year's spending was loan-funded (Pinjaman); the rest was paid directly (Cara Langsung). The total cost of all projects (Kos Keseluruhan) is RM 501.53 bn.
Every development vote
Hover a figure for the exact amount, or open a vote for every project to the sen.