Jabatan Perkhidmatan Awam
A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2018, from the audited Statement of Development Expenditure.
Estimate 2018Anggaran
RM 27.84 m
Spent 2018Sebenar
RM 27.34 m
98.2% of the estimate
Total cost of projectsKos Keseluruhan
RM 412.54 m
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2018Anggaran | Spent 2018Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Institut Tadbiran Awam Negara | RM 267,650,000.00 | RM 17,819,938.00 | RM 17,336,289.65 | 97.3% | RM 93,046,210.53 | JANM 2018, pp. 208–209 |
| 00200 | Komputer Induk JPA | RM 140,692,000.00 | RM 9,921,836.00 | RM 9,908,024.02 | 99.9% | RM 45,160,736.35 | JANM 2018, pp. 208–209 |
| 00300 | Kajian Perkhidmatan Awam (Kajian JPA) | RM 4,200,000.00 | RM 99,122.00 | RM 93,806.54 | 94.6% | RM 93,806.54 | JANM 2018, pp. 208–209 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2018, Statement of Development Expenditure (Lampiran 2).