Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00100Institut Tadbiran Awam NegaraRM 271,850,000.00RM 8,483,378.00RM 8,471,651.98
99.9%
RM 124,622,698.83JANM 2020, pp. 194–195
00200Komputer Induk JPARM 140,692,000.00RM 6,563,645.00RM 6,559,823.58
99.9%
RM 60,215,898.49JANM 2020, pp. 194–195
00300Kajian Perkhidmatan Awam (Kajian JPA)RM 9,730,000.00RM 2,704,410.00RM 2,698,535.00
99.8%
RM 4,488,831.97JANM 2020, pp. 194–195

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2020, Statement of Development Expenditure (Lampiran 2).