Kementerian Komunikasi dan Multimedia
A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2018, from the audited Statement of Development Expenditure.
The same code is printed as Kementerian Komunikasi dan Digital in 2023 and Kementerian Komunikasi in 2024–2025.
All development votes in 2018 · Operating vote B.47 · P.47 in Budget 2027
Estimate 2018Anggaran
RM 750.20 m
Spent 2018Sebenar
RM 715.40 m
95.4% of the estimate
Total cost of projectsKos Keseluruhan
RM 7.68 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2018Anggaran | Spent 2018Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 01401 | Bangunan RTM Seremban | RM 2,439,324.00 | RM 0.00 | RM 0.00 | RM 2,439,324.00 | JANM 2018, pp. 232–233 | |
| 01600 | Cybersecurity Malaysia | RM 296,974,063.00 | RM 35,000,000.00 | RM 35,000,000.00 | 100.0% | RM 35,000,000.00 | JANM 2018, pp. 232–233 |
| 02000 | Tapak Stesen Pemancar TV RTM di Gulai Mukim Soh Daerah Sik Kedah | RM 31,429.00 | RM 0.00 | RM 0.00 | RM 31,429.00 | JANM 2018, pp. 232–233 | |
| 02001 | Jabatan Penyiaran Malaysia Tawau | RM 20,573,547.00 | RM 0.00 | RM 0.00 | RM 480,881.94 | JANM 2018, pp. 232–233 | |
| 02002 | Bangunan Penyiaran RTM Bintulu | RM 21,000,000.00 | RM 348,182.00 | RM 347,933.65 | 99.9% | RM 415,549.91 | JANM 2018, pp. 232–233 |
| 02003 | Bangunan Jabatan Penyiaran RTM Sandakan | RM 21,000,000.00 | RM 0.00 | RM 0.00 | RM 38,634.00 | JANM 2018, pp. 232–233 | |
| 02004 | Van Siaran Luar RTM Kuching | RM 12,000,000.00 | RM 0.00 | RM 0.00 | RM 11,061,663.41 | JANM 2018, pp. 232–233 | |
| 02005 | Electronic News Gathering (ENG) | RM 12,000,000.00 | RM 0.00 | RM 0.00 | RM 9,000,595.58 | JANM 2018, pp. 232–233 | |
| 02006 | Sistem Penyiaran RTM Johor | RM 9,900,000.00 | RM 0.00 | RM 0.00 | RM 8,956,702.06 | JANM 2018, pp. 232–233 | |
| 02007 | Peralatan Studio Radio RTM Sarawak | RM 8,000,000.00 | RM 0.00 | RM 0.00 | RM 6,692,161.70 | JANM 2018, pp. 232–233 | |
| 02008 | Bangunan Penyiaran RTM Langkawi | RM 6,500,000.00 | RM 0.00 | RM 0.00 | RM 72,874.49 | JANM 2018, pp. 234–235 | |
| 02009 | Sistem Arkib Audio Visual Digital | RM 5,000,000.00 | RM 0.00 | RM 0.00 | RM 4,907,883.05 | JANM 2018, pp. 234–235 | |
| 02010 | Sistem Suntingan Non-Linear Penerbitan TV | RM 4,300,000.00 | RM 0.00 | RM 0.00 | RM 3,794,282.67 | JANM 2018, pp. 234–235 | |
| 02011 | Peralatan Unit Siaran Luar Radio | RM 4,025,734.00 | RM 0.00 | RM 0.00 | RM 4,025,734.23 | JANM 2018, pp. 234–235 | |
| 02012 | Sistem Visual Graphic-On-Air dan Pangkalan Data | RM 1,800,000.00 | RM 0.00 | RM 0.00 | RM 1,697,307.00 | JANM 2018, pp. 234–235 | |
| 02013 | Sistem Rangkaian Bersepadu Angkasapuri | RM 7,100,000.00 | RM 0.00 | RM 0.00 | RM 5,283,944.00 | JANM 2018, pp. 234–235 | |
| 02014 | Sistem Penyiaran TV Digital Berdefinisi Tinggi | RM 38,705,000.00 | RM 30,875,000.00 | RM 26,739,988.61 | 86.6% | RM 26,739,988.61 | JANM 2018, pp. 234–235 |
| 02015 | Pembangunan Semula Kompleks Angkasapuri Sebagai Bandar Media (Media City) | RM 1,887,299,811.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2018, pp. 234–235 | |
| 02016 | Peralatan dan Sistem Bahan Penerbitan Program TV Angkasapuri | RM 920,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2018, pp. 234–235 | |
| 02110 | Pengisian Liputan Radio | RM 6,400,000.00 | RM 0.00 | RM 0.00 | RM 2,847,628.77 | JANM 2018, pp. 234–235 | |
| 02701 | HD Broadcast Link For TV and News Production | RM 11,000,000.00 | RM 0.00 | RM 0.00 | RM 4,077,289.59 | JANM 2018, pp. 234–235 | |
| 02900 | Kompleks Penyiaran Negeri Perlis | RM 21,000,000.00 | RM 6,825,117.00 | RM 5,956,709.76 | 87.3% | RM 6,049,792.49 | JANM 2018, pp. 234–235 |
| 03210 | Kompleks Penerangan Komunikasi dan Kebudayaan Wilayah Persekutuan Labuan | RM 10,500,000.00 | RM 4,185,442.00 | RM 4,185,361.60 | 100.0% | RM 6,352,848.70 | JANM 2018, pp. 234–235 |
| 05700 | Studio A HDTV Production System | RM 10,151,453.00 | RM 0.00 | RM 0.00 | RM 8,090,340.40 | JANM 2018, pp. 234–235 | |
| 05900 | Pembangunan Makmal Grafik dan Multimedia IPPTAR | RM 750,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2018, pp. 234–235 | |
| 06000 | Pembinaan Bangunan Pejabat Penerangan Daerah | RM 18,600,000.00 | RM 3,264,170.00 | RM 3,221,674.03 | 98.7% | RM 7,811,738.17 | JANM 2018, pp. 234–235 |
| 06001 | Pembinaan Bangunan Baru Pejabat Penerangan Daerah Batang | RM 3,000,000.00 | RM 0.00 | RM 0.00 | RM 272,613.16 | JANM 2018, pp. 234–235 | |
| 06002 | Pusat Media dan Komunikasi Bergerak | RM 2,650,000.00 | RM 0.00 | RM 0.00 | RM 694,229.76 | JANM 2018, pp. 234–235 | |
| 06003 | Menaiktaraf Pejabat Penerangan Negeri, Bahagian dan Daerah Seluruh Negara | RM 10,000,000.00 | RM 8,073,887.00 | RM 7,205,908.49 | 89.3% | RM 8,674,579.97 | JANM 2018, pp. 234–235 |
| 06004 | Peningkatan Sistem Peralatan Siaraya Digital, Jabatan Penerangan Malaysia | RM 1,500,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2018, pp. 234–235 | |
| 06100 | Pembangunan Sistem Editorial BERNAMA (BEST) (FASA II) | RM 8,500,000.00 | RM 0.00 | RM 0.00 | RM 1,500,000.00 | JANM 2018, pp. 234–235 | |
| 06501 | Sistem Pengurusan Sumber Manusia BERNAMA | RM 2,000,000.00 | RM 0.00 | RM 0.00 | RM 2,000,000.00 | JANM 2018, pp. 234–235 | |
| 06502 | Peningkatan Sistem Bernama.com dan Aplikasi Pintar | RM 1,511,749.00 | RM 0.00 | RM 0.00 | RM 1,511,749.00 | JANM 2018, pp. 234–235 | |
| 06503 | Pembelian Kenderaan BERNAMA | RM 1,000,000.00 | RM 0.00 | RM 0.00 | RM 1,000,000.00 | JANM 2018, pp. 234–235 | |
| 06504 | Sistem Berita Multimedia News Centre (MNC) | RM 6,581,000.00 | RM 4,200,000.00 | RM 4,200,000.00 | 100.0% | RM 6,200,000.00 | JANM 2018, pp. 234–235 |
| 06505 | Peralatan dan Perkhidmatan Foto "State of The Art" BERNAMA | RM 4,768,406.00 | RM 600,000.00 | RM 600,000.00 | 100.0% | RM 4,699,993.50 | JANM 2018, pp. 234–235 |
| 06506 | Sistem Perakaunan BERNAMA | RM 3,127,000.00 | RM 2,109,400.00 | RM 2,109,400.00 | 100.0% | RM 3,127,000.00 | JANM 2018, pp. 234–235 |
| 06507 | Pusat Pemantauan Keselamatan Rangkaian (NOC) BERNAMA | RM 500,000.00 | RM 180,000.00 | RM 180,000.00 | 100.0% | RM 500,000.00 | JANM 2018, pp. 234–235 |
| 06508 | Membangun dan Menaiktaraf Bangunan Wisma BERNAMA | RM 10,000,000.00 | RM 2,772,650.00 | RM 2,772,650.00 | 100.0% | RM 2,772,650.00 | JANM 2018, pp. 234–235 |
| 06111 | Pembangunan Sistem BERNAMA TV | RM 21,800,000.00 | RM 0.00 | RM 0.00 | RM 17,440,000.00 | JANM 2018, pp. 234–235 | |
| 09000 | Pelbagai Suntikan Ekuiti | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2018, pp. 234–235 | |
| 10600 | Projek Kerajaan Elektronik | RM 253,930,874.00 | RM 259,887,195.00 | RM 253,930,873.78 | 97.7% | RM 253,930,873.78 | JANM 2018, pp. 234–235 |
| 30001 | Penambahbaikan Malaysian Emergency Response Services (MERS) 999 | RM 114,487,087.00 | RM 0.00 | RM 0.00 | RM 106,976.28 | JANM 2018, pp. 234–235 | |
| 30000 | Projek Perkhidmatan Panggilan Kecemasan (PPK) | RM 496,000,000.00 | RM 0.00 | RM 0.00 | RM 5,095,335.52 | JANM 2018, pp. 234–235 | |
| 31000 | Projek Jalur Lebar Berkelajuan Tinggi | RM 570,000,000.00 | RM 50,000,000.00 | RM 50,000,000.00 | 100.0% | RM 115,857,600.00 | JANM 2018, pp. 234–235 |
| 31001 | Infrastruktur Komunikasi Bandar Pintar | RM 2,000,000.00 | RM 393,122.00 | RM 393,121.51 | 100.0% | RM 430,979.41 | JANM 2018, pp. 234–235 |
| 32000 | Schoolnet Fasa 2 | RM 217,249,700.00 | RM 10,000,000.00 | RM 10,000,000.00 | 100.0% | RM 45,000,000.00 | JANM 2018, pp. 234–235 |
| 33000 | Multimedia Development Corporation (MDeC) | RM 843,863,578.00 | RM 64,608,500.00 | RM 64,608,500.00 | 100.0% | RM 290,089,910.68 | JANM 2018, pp. 234–235 |
| 34000 | MYNIC | RM 26,542,341.00 | RM 7,416,500.00 | RM 7,416,500.00 | 100.0% | RM 19,163,600.00 | JANM 2018, pp. 234–235 |
| 47000 | FINAS | RM 426,265,000.00 | RM 57,375,461.00 | RM 57,375,460.50 | 100.0% | RM 153,485,148.50 | JANM 2018, pp. 234–235 |
| 53000 | Dasar Industri Kreatif Negara | RM 1,120,000,000.00 | RM 101,981,000.00 | RM 101,980,045.65 | 100.0% | RM 232,502,993.92 | JANM 2018, pp. 234–235 |
| 66000 | Kompleks KKMM (4G9) | RM 1,016,526,309.00 | RM 47,207,654.00 | RM 47,207,653.48 | 100.0% | RM 95,790,287.16 | JANM 2018, pp. 234–235 |
| 94000 | NKEA | RM 81,050,000.00 | RM 52,901,546.00 | RM 29,972,343.12 | 56.7% | RM 43,972,343.12 | JANM 2018, pp. 234–235 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2018, Statement of Development Expenditure (Lampiran 2).