Skip to content

Kementerian Sumber Manusia

A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2019, from the audited Statement of Development Expenditure.

Estimate 2019Anggaran
RM 323.47 m
Spent 2019Sebenar
RM 322.74 m
99.8% of the estimate
Total cost of projectsKos Keseluruhan
RM 4.17 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 1.74 bn
Totals as printed, JANM 2019, pp. 190–191

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00100Institut Kemahiran Belia Negara (IKBN)RM 523,359,553.58RM 0.00RM 0.00RM 28,631,328.39JANM 2019, pp. 188–189
00200Naiktaraf Institut Kemahiran Tinggi Belia Negara (IKTBN), SepangRM 48,696,047.00RM 0.00RM 0.00RM 1,966,926.00JANM 2019, pp. 188–189
00600Kemajuan Guna Tenaga ManusiaRM 1,891,098,653.00RM 214,071,900.00RM 214,071,600.20
100.0%
RM 1,190,243,280.94JANM 2019, pp. 188–189
01700Peluasan dan Peningkatan Penguatkuasaan Keselamatan & Kesihatan PekerjaanRM 22,375,000.00RM 3,926,000.00RM 3,888,120.19
99.0%
RM 14,178,097.56JANM 2019, pp. 188–189
02000Pembangunan Bangunan Tambahan Pusat Pameran Multimedia OSH di Ibu Pejabat NIOSH Bangi Selangor (Bangunan Tambahan Bertingkat, Blok Hostel dan NIOSH Annex)RM 83,425,000.00RM 3,800,000.00RM 3,800,000.00
100.0%
RM 18,800,000.00JANM 2019, pp. 188–189
02300Pembangunan Fasa 1 Kampus Cawangan NIOSH Kertih, TerengganuRM 13,360,000.00RM 0.00RM 0.00RM 2,000,000.00JANM 2019, pp. 188–189
03200Pembangunan Standard dan Kurikulum Sumber Manusia MahirRM 53,500,000.00RM 11,502,800.00RM 11,493,291.50
99.9%
RM 31,255,571.48JANM 2019, pp. 188–189
04200Pengkomputeran KSM Fasa IIRM 28,000,000.00RM 0.00RM 0.00RM 15,021,784.57JANM 2019, pp. 188–189
04700Institut Latihan Perindustrian (ILP) SelangorRM 13,000,000.00RM 32,800.00RM 32,690.90
99.7%
RM 1,748,054.21JANM 2019, pp. 188–189
04800Institut Latihan Perindustrian (ILP) SandakanRM 9,000,000.00RM 6,200.00RM 6,172.38
99.5%
RM 519,127.44JANM 2019, pp. 188–189
05300Program Latihan Teknologi Tinggi (ADTEC) BintuluRM 1,300,000.00RM 277,000.00RM 261,250.00
94.3%
RM 1,247,947.04JANM 2019, pp. 188–189
05500Pusat Latihan Teknologi Tinggi (ADTEC) JerantutRM 70,500,000.00RM 395,100.00RM 393,541.00
99.6%
RM 3,598,779.02JANM 2019, pp. 188–189
05700Institut Latihan Perindustrian (ILP) MarangRM 105,655,000.00RM 0.00RM 0.00RM 4,776,724.79JANM 2019, pp. 190–191
05800Naik Taraf Institut Latihan Jabatan Tenaga Manusia di JohorRM 73,184,000.00RM 385,900.00RM 380,376.47
98.6%
RM 15,304,560.63JANM 2019, pp. 190–191
05900Naik Taraf Institut Latihan Jabatan Tenaga Manusia di KedahRM 46,298,600.00RM 824,100.00RM 803,137.69
97.5%
RM 7,234,868.99JANM 2019, pp. 190–191
06000Naik Taraf Institut Latihan Jabatan Tenaga Manusia di Kota BharuRM 12,200,000.00RM 26,800.00RM 26,748.04
99.8%
RM 1,923,389.41JANM 2019, pp. 190–191
06100Naik Taraf Institut Latihan Jabatan Tenaga Manusia di MelakaRM 45,358,500.00RM 438,200.00RM 427,585.48
97.6%
RM 10,424,291.43JANM 2019, pp. 190–191
06200Naik Taraf Institut Latihan Jabatan Tenaga Manusia di Negeri SembilanRM 12,300,000.00RM 2,700.00RM 2,640.00
97.8%
RM 982,276.00JANM 2019, pp. 190–191
06300Naik Taraf Institut Latihan Jabatan Tenaga Manusia di PahangRM 27,589,100.00RM 89,100.00RM 89,059.01
100.0%
RM 2,023,439.00JANM 2019, pp. 190–191
06400Naik Taraf Institut Latihan Jabatan Tenaga Manusia di Pulau PinangRM 22,150,160.00RM 25,000.00RM 25,000.00
100.0%
RM 4,711,401.60JANM 2019, pp. 190–191
06500Naik Taraf Institut Latihan Jabatan Tenaga Manusia Ipoh, PerakRM 14,959,700.00RM 34,300.00RM 33,895.01
98.8%
RM 940,124.97JANM 2019, pp. 190–191
06600Naik Taraf Institut Latihan Jabatan Tenaga Manusia KangarRM 13,700,000.00RM 6,000.00RM 0.00
0.0%
RM 1,320,935.68JANM 2019, pp. 190–191
06700Naik Taraf Pusat Latihan Teknologi Tinggi (ADTEC) di SelangorRM 12,250,000.00RM 35,000.00RM 30,567.11
87.3%
RM 1,699,452.19JANM 2019, pp. 190–191
06800Naik Taraf Institut Latihan Jabatan Tenaga Manusia Kuala TerengganuRM 14,000,000.00RM 10,000.00RM 6,877.00
68.8%
RM 1,003,312.06JANM 2019, pp. 190–191
06900Naik Taraf Institut Latihan Jabatan Tenaga Manusia di SabahRM 40,000,000.00RM 129,700.00RM 115,495.36
89.0%
RM 6,483,702.97JANM 2019, pp. 190–191
07000Naik Taraf Institut Latihan Jabatan Tenaga Manusia di SarawakRM 315,300,000.00RM 19,703,800.00RM 19,703,744.13
100.0%
RM 60,595,052.77JANM 2019, pp. 190–191
07100Naik Taraf Institut Latihan Jabatan Tenaga Manusia Kuala LumpurRM 15,000,000.00RM 0.00RM 0.00RM 2,398,514.61JANM 2019, pp. 190–191
07300Program Latihan Teknologi Tinggi (ADTEC) KemamanRM 103,000,000.00RM 0.00RM 0.00RM 1,565,820.36JANM 2019, pp. 190–191
07400Institut Latihan Perindustrian Vokasional Kebangsaan (ILPVK) Sungai PetaniRM 22,000,000.00RM 6,500.00RM 6,254.00
96.2%
RM 4,449,095.23JANM 2019, pp. 190–191
07500Program Peningkatan dan Penambahbaikan Kualiti LatihanRM 38,465,000.00RM 3,007,200.00RM 2,913,965.54
96.9%
RM 19,800,260.31JANM 2019, pp. 190–191
08000Pembangunan Sumber Manusia Jabatan Perhubungan Perusahaan (JPP)RM 47,500,000.00RM 605,600.00RM 604,677.41
99.8%
RM 23,413,072.12JANM 2019, pp. 190–191
08100Sistem Gaji Yang Dikaitkan Dengan Produktiviti/Prestasi (PLWS)RM 4,616,000.00RM 930,000.00RM 921,859.66
99.1%
RM 2,996,219.27JANM 2019, pp. 190–191
08300Projek Membina 6 Pejabat Tenaga Kerja BaruRM 26,527,667.00RM 221,400.00RM 221,195.05
99.9%
RM 3,912,510.36JANM 2019, pp. 190–191
08400Projek Skim Grant Galakan untuk Orang Kurang Upaya (OKU)RM 10,000,000.00RM 1,771,100.00RM 1,770,432.43
100.0%
RM 7,651,517.04JANM 2019, pp. 190–191
08800Pengkomputeran KSM (SBMK Fasa III)RM 20,819,000.00RM 3,488,900.00RM 3,488,871.40
100.0%
RM 9,902,950.56JANM 2019, pp. 190–191
09000Tanah dan Kerja AwalanRM 2,000,000.00RM 835,500.00RM 759,732.19
90.9%
RM 759,732.19JANM 2019, pp. 190–191
09200Japan-Malaysia Training Institute(JMTI), Bukit Minyak, Pulau PinangRM 15,000,000.00RM 0.00RM 0.00RM 2,554,506.00JANM 2019, pp. 190–191
09300Pusat Latihan Pengajar dan Latihan Lanjutan (CIAST)RM 114,900,000.00RM 21,861,500.00RM 21,448,384.48
98.1%
RM 78,394,793.33JANM 2019, pp. 190–191
09500Kemajuan Guna Tenaga ManusiaRM 55,000,000.00RM 1,250,000.00RM 1,250,000.00
100.0%
RM 26,250,000.00JANM 2019, pp. 190–191
09600Keselamatan Kesihatan dan Kesejahteraan PekerjaanRM 5,000,000.00RM 0.00RM 0.00RM 4,573,496.53JANM 2019, pp. 190–191
90000Talent CorporationRM 68,890,500.00RM 1,000,000.00RM 1,000,000.00
100.0%
RM 55,300,000.00JANM 2019, pp. 190–191
95000PPP/PFI - Bayaran Sewaan BangunanRM 104,199,674.00RM 32,767,300.00RM 32,767,239.12
100.0%
RM 66,517,495.42JANM 2019, pp. 190–191

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Development Expenditure (Lampiran 2).