A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2022, from the audited Statement of Development Expenditure.

Estimate 2022Anggaran
RM 329.83 m
Spent 2022Sebenar
RM 321.05 m
97.3% of the estimate
Total cost of projectsKos Keseluruhan
RM 3.01 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 600.26 m
Totals as printed, JANM 2022, pp. 210–211

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00600Kemajuan Guna Tenaga ManusiaRM 1,842,531,764.00RM 213,209,058.00RM 207,430,943.20
97.3%
RM 362,468,906.08JANM 2022, pp. 208–209
01700Peluasan dan Peningkatan Penguatkuasaan Keselamatan dan Kesihatan PekerjaanRM 7,800,000.00RM 1,149,200.00RM 1,149,136.46
100.0%
RM 4,371,944.57JANM 2022, pp. 208–209
03200Pembangunan Standard dan Kurikulum Sumber Manusia MahirRM 0.00RM 0.00RM 0.00RM 80,450.00JANM 2022, pp. 208–209
04300Institut Latihan Perindustrian Nibong Tebal P.PinangRM 2,755,000.00RM 7,500.00RM 0.00
0.0%
RM 2,149,322.00JANM 2022, pp. 208–209
04700Institut Latihan Perindustrian (ILP) SelangorRM 10,000,000.00RM 0.00RM 0.00RM 107,680.54JANM 2022, pp. 208–209
05500Pusat Latihan Teknologi Tinggi (ADTEC) JerantutRM 79,363,840.00RM 257,100.00RM 257,004.00
100.0%
RM 363,023.00JANM 2022, pp. 208–209
05700Institut Latihan Perindustrian (ILP) MarangNote: P.46 – Butiran 05700 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluanRM 161,060,293.33RM 470.00RM 420.00
89.4%
RM 12,320.00JANM 2022, pp. 210–211
05800Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di JohorRM 47,784,000.00RM 3,417,047.00RM 3,416,770.69
100.0%
RM 12,668,381.27JANM 2022, pp. 210–211
05900Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di KedahRM 29,023,303.56RM 4,330,990.00RM 4,330,795.30
100.0%
RM 5,397,665.30JANM 2022, pp. 210–211
06000Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di Kota BharuRM 2,200,000.00RM 574,360.00RM 571,560.00
99.5%
RM 1,442,292.00JANM 2022, pp. 210–211
06100Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di MelakaRM 19,498,500.00RM 7,454,314.00RM 7,434,167.42
99.7%
RM 13,238,567.42JANM 2022, pp. 210–211
06200Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di Negeri SembilanRM 2,300,000.00RM 23,011.00RM 23,010.90
100.0%
RM 1,193,445.29JANM 2022, pp. 210–211
06400Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di Pulau PinangRM 0.00RM 0.00RM 0.00RM 0.00JANM 2022, pp. 210–211
06500Menaik Taraf Institut Latihan Jabatan Tenaga Manusia IpohRM 3,743,000.00RM 1,164,260.00RM 1,164,222.10
100.0%
RM 1,971,839.80JANM 2022, pp. 210–211
06600Menaik Taraf Institut Latihan Jabatan Tenaga Manusia KangarRM 4,019,000.00RM 1,800,000.00RM 1,800,000.00
100.0%
RM 2,154,600.00JANM 2022, pp. 210–211
06700Menaik Taraf Pusat Latihan Teknologi Tinggi (ADTEC) SelangorRM 0.00RM 0.00RM 0.00RM 141,800.00JANM 2022, pp. 210–211
06800Menaik Taraf Institut Latihan Jabatan Tenaga Manusia Kuala TerengganuRM 8,000,000.00RM 363,600.00RM 359,628.28
98.9%
RM 4,304,456.85JANM 2022, pp. 210–211
06900Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di SabahRM 15,000,000.00RM 734,500.00RM 0.00
0.0%
RM 350,644.00JANM 2022, pp. 210–211
07000Menaik Taraf Institut Latihan Jabatan Tenaga Manusia di SarawakRM 289,300,000.00RM 36,017,800.00RM 33,907,367.42
94.1%
RM 77,234,785.57JANM 2022, pp. 210–211
07300Pusat Latihan Teknologi Tinggi (ADTEC) KemamanRM 102,578,496.44RM 0.00RM 0.00RM 750,291.00JANM 2022, pp. 210–211
07400Institut Latihan Perindustrian Vokasional Kebangsaan (ILPVK) Sungai PetaniRM 12,000,000.00RM 0.00RM 0.00RM 772,920.00JANM 2022, pp. 210–211
07500Program Peningkatan dan Penambahbaikan Kualiti LatihanRM 5,265,000.00RM 60,200.00RM 37,716.00
62.6%
RM 907,697.00JANM 2022, pp. 210–211
08000Pembangunan Sumber Manusia Jabatan Perhubungan Perusahaan (JPP)RM 31,700,000.00RM 2,939,800.00RM 2,938,364.80
100.0%
RM 3,189,911.08JANM 2022, pp. 210–211
08300Projek Membina 6 Pejabat Tenaga Kerja BaruRM 112,173,843.75RM 15,948,900.00RM 15,899,624.70
99.7%
RM 28,275,689.01JANM 2022, pp. 210–211
08800Pengkomputeran KSM (SMBK Fasa III)RM 10,000,000.00RM 1,834,900.00RM 1,785,252.00
97.3%
RM 2,412,772.00JANM 2022, pp. 210–211
09300Pusat Latihan Pengajar dan Latihan Lanjutan (CIAST)RM 7,049,000.00RM 201,700.00RM 201,627.52
100.0%
RM 201,627.52JANM 2022, pp. 210–211
09510Institut Latihan Perindustrian LabuanRM 29,600,000.00RM 2,597,800.00RM 2,597,748.00
100.0%
RM 2,602,634.50JANM 2022, pp. 210–211
95000Private Public Partnership/Private Finance (PPP/PFI)RM 178,730,500.00RM 35,746,100.00RM 35,746,079.04
100.0%
RM 71,492,158.08JANM 2022, pp. 210–211

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2022, Statement of Development Expenditure (Lampiran 2).