Kementerian Dalam Negeri
A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2019, from the audited Statement of Development Expenditure.
Estimate 2019Anggaran
RM 2.56 bn
Spent 2019Sebenar
RM 2.43 bn
94.9% of the estimate
Total cost of projectsKos Keseluruhan
RM 23.54 bn
By group
The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.
| Group | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|
| Pengurusan Dasar Dalam Negeri | RM 152.72 m | RM 152.42 m | 99.8% | RM 330.20 m | JANM 2019, pp. 194–195 |
| Agensi Antidadah Kebangsaan | RM 28.96 m | RM 28.80 m | 99.5% | RM 76.21 m | JANM 2019, pp. 194–195 |
| Polis Diraja Malaysia | RM 1.61 bn | RM 1.53 bn | 95.3% | RM 3.25 bn | JANM 2019, pp. 194–195 |
| Imigresen | RM 263.96 m | RM 245.86 m | 93.2% | RM 725.01 m | JANM 2019, pp. 194–195 |
| Pendaftaran Negara | RM 40.61 m | RM 37.52 m | 92.4% | RM 105.37 m | JANM 2019, pp. 194–195 |
| Penjara | RM 78.55 m | RM 62.70 m | 79.8% | RM 288.08 m | JANM 2019, pp. 196–197 |
| Pertahanan Awam | RM 384.60 m | RM 366.73 m | 95.3% | RM 1.85 bn | JANM 2019, pp. 196–197 |
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
Pengurusan Dasar Dalam Negeri3 projectsEstimate RM 152.72 m · Spent RM 152.42 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 01000 | Ibu Pejabat Kementerian Dalam Negeri | RM 405,193,101.80 | RM 152,722,500.00 | RM 152,422,498.50 | 99.8% | RM 312,159,022.27 | JANM 2019, pp. 194–195 |
| 02300 | Menaiktaraf Peralatan Tonton Tapis Lembaga Penapis Filem | RM 1,225,000.00 | RM 0.00 | RM 0.00 | RM 1,039,960.00 | JANM 2019, pp. 194–195 | |
| 05000 | Pengkomputeran KDN | RM 25,000,000.00 | RM 0.00 | RM 0.00 | RM 17,000,000.00 | JANM 2019, pp. 194–195 |
Agensi Antidadah Kebangsaan1 projectEstimate RM 28.96 m · Spent RM 28.80 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 02000 | Agensi Antidadah Kebangsaan | RM 485,973,858.00 | RM 28,962,000.00 | RM 28,802,037.75 | 99.5% | RM 76,210,924.30 | JANM 2019, pp. 194–195 |
Polis Diraja Malaysia16 projectsEstimate RM 1.61 bn · Spent RM 1.53 bn
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 11000 | Ibu Pejabat Polis (PDRM) | RM 2,054,425,476.00 | RM 218,194,194.00 | RM 203,578,167.76 | 93.3% | RM 683,508,905.48 | JANM 2019, pp. 194–195 |
| 12000 | Balai-balai dan Pondok Polis (PDRM) | RM 252,555,500.00 | RM 9,487,760.00 | RM 8,287,461.70 | 87.3% | RM 86,504,919.03 | JANM 2019, pp. 194–195 |
| 13000 | Pusat Latihan (PDRM)Note: P.62– Butiran 13000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2019 telah dimasuk kira sebagai pendahuluan. | RM 162,880,000.00 | RM 3,960,010.00 | RM 3,767,500.00 | 95.1% | RM 16,346,691.54 | JANM 2019, pp. 194–195 |
| 14000 | Pangkalan Marin (PDRM) | RM 87,500.00 | RM 0.00 | RM 0.00 | RM 87,481.33 | JANM 2019, pp. 194–195 | |
| 17000 | Pasukan Gerakan Am (PDRM) | RM 633,100,000.00 | RM 22,800,000.00 | RM 21,334,343.30 | 93.6% | RM 41,365,141.88 | JANM 2019, pp. 194–195 |
| 18000 | Pembaikan dan Ubahsuai (PDRM) Kuala Lumpur | RM 433,762,943.00 | RM 53,411,146.00 | RM 52,245,843.28 | 97.8% | RM 69,137,858.60 | JANM 2019, pp. 194–195 |
| 19000 | Lanci-lanci Polis (PDRM) | RM 295,964,000.00 | RM 22,648,000.00 | RM 22,148,415.60 | 97.8% | RM 48,286,807.36 | JANM 2019, pp. 194–195 |
| 20000 | Alat-alat Perhubungan Radio (PDRM) | RM 1,796,313,700.00 | RM 27,317,775.00 | RM 8,703,260.00 | 31.9% | RM 187,775,243.86 | JANM 2019, pp. 194–195 |
| 21000 | Senjata Api dan Peluru (PDRM) | RM 532,421,884.00 | RM 104,295,300.00 | RM 97,645,810.00 | 93.6% | RM 265,089,526.84 | JANM 2019, pp. 194–195 |
| 21001 | Peralatan Sokongan Persenjataan (PDRM) | RM 18,825,000.00 | RM 0.00 | RM 0.00 | RM 4,385,000.00 | JANM 2019, pp. 194–195 | |
| 22000 | Kenderaan (PDRM) | RM 447,030,000.00 | RM 72,309,811.00 | RM 60,252,308.96 | 83.3% | RM 95,856,928.66 | JANM 2019, pp. 194–195 |
| 23000 | Kapal-kapal Terbang (PDRM) | RM 478,560,000.00 | RM 102,725,365.00 | RM 96,350,265.00 | 93.8% | RM 345,642,883.38 | JANM 2019, pp. 194–195 |
| 24000 | Alat Bantuan Teknik (PDRM) | RM 512,939,300.00 | RM 16,761,443.00 | RM 7,401,006.59 | 44.1% | RM 156,170,420.71 | JANM 2019, pp. 194–195 |
| 25000 | Sistem Teknologi Maklumat (PDRM) | RM 1,015,441,000.00 | RM 31,587,034.00 | RM 28,373,875.00 | 89.8% | RM 321,281,092.68 | JANM 2019, pp. 194–195 |
| 26000 | Sewaan Projek Built Lease and Transfer (BLT) PDRM | RM 1,847,591,200.00 | RM 923,795,600.00 | RM 923,795,575.17 | 100.0% | RM 923,795,575.17 | JANM 2019, pp. 194–195 |
| 78000 | Perumahan Polis Diraja Malaysia | RM 62,440,000.00 | RM 0.00 | RM 0.00 | RM 2,859,518.04 | JANM 2019, pp. 194–195 |
Imigresen4 projectsEstimate RM 263.96 m · Spent RM 245.86 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 35000 | Pejabat-pejabat dan Rumah Kediaman (Imigresen) | RM 1,895,711,584.00 | RM 136,299,750.00 | RM 118,425,115.35 | 86.9% | RM 321,638,621.99 | JANM 2019, pp. 194–195 |
| 36000 | Perolehan Kenderaan JIMNote: P.62– Butiran 36000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2019 telah dimasuk kira sebagai pendahuluan. | RM 20,950,000.00 | RM 2,293,892.00 | RM 2,293,891.53 | 100.0% | RM 13,243,891.53 | JANM 2019, pp. 194–195 |
| 37000 | Pengkomputeran (Imigresen) | RM 1,904,134,976.00 | RM 123,864,220.00 | RM 123,864,219.22 | 100.0% | RM 387,988,107.64 | JANM 2019, pp. 194–195 |
| 38000 | Pembaikan dan Ubah Suai (Imigresen) | RM 50,780,000.00 | RM 1,500,000.00 | RM 1,281,511.05 | 85.4% | RM 2,139,255.92 | JANM 2019, pp. 194–195 |
Pendaftaran Negara2 projectsEstimate RM 40.61 m · Spent RM 37.52 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 45000 | Pejabat-pejabat dan Rumah Kediaman (JPN) | RM 332,918,008.90 | RM 40,606,173.00 | RM 37,517,807.16 | 92.4% | RM 79,972,194.88 | JANM 2019, pp. 194–195 |
| 47000 | Pengkomputeran dan Kad Pintar (JPN) | RM 142,200,000.00 | RM 0.00 | RM 0.00 | RM 25,397,485.59 | JANM 2019, pp. 194–195 |
Penjara7 projectsEstimate RM 78.55 m · Spent RM 62.70 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 55000 | Ibu Pejabat Jabatan Penjara Kajang, SelangorNote: P.62– Butiran 55000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2019 telah dimasuk kira sebagai pendahuluan. | RM 64,530,000.00 | RM 740,010.00 | RM 378,870.00 | 51.2% | RM 51,759,002.66 | JANM 2019, pp. 196–197 |
| 56000 | Bangunan-bangunan Penjara | RM 703,278,351.94 | RM 66,763,220.00 | RM 59,901,398.03 | 89.7% | RM 90,109,968.92 | JANM 2019, pp. 196–197 |
| 58000 | Sekolah Henry Gurney | RM 53,600,000.00 | RM 0.00 | RM 0.00 | RM 81,894.14 | JANM 2019, pp. 196–197 | |
| 60000 | Pusat Latihan Penjara | RM 25,000,000.00 | RM 327,640.00 | RM 327,638.47 | 100.0% | RM 327,638.47 | JANM 2019, pp. 196–197 |
| 62000 | Langkah-langkah Keselamatan (Penjara) | RM 227,550,000.00 | RM 8,285,360.00 | RM 1,110,200.00 | 13.4% | RM 122,185,823.33 | JANM 2019, pp. 196–197 |
| 64000 | Pembaikan dan Ubahsuai (Penjara) | RM 61,183,000.00 | RM 2,432,000.00 | RM 983,045.83 | 40.4% | RM 23,478,393.34 | JANM 2019, pp. 196–197 |
| 68000 | Unit Keselamatan dan Anjing Pengesan | RM 5,000,000.00 | RM 0.00 | RM 0.00 | RM 135,000.00 | JANM 2019, pp. 196–197 |
Pertahanan Awam5 projectsEstimate RM 384.60 m · Spent RM 366.73 m
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2019Anggaran | Spent 2019Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 03000 | Agensi Kawalan Sempadan Malaysia (AKSEM) | RM 203,000,000.00 | RM 75,076.00 | RM 64,786.66 | 86.3% | RM 64,786.66 | JANM 2019, pp. 196–197 |
| 04000 | RELA | RM 271,920,000.00 | RM 12,538,000.00 | RM 4,779,856.45 | 38.1% | RM 15,429,358.78 | JANM 2019, pp. 196–197 |
| 08800 | Pembangunan ESSCOM | RM 1,423,644,500.00 | RM 7,204,371.00 | RM 4,736,577.91 | 65.8% | RM 113,008,065.51 | JANM 2019, pp. 196–197 |
| 80000 | Program Bandar Selamat | RM 150,000,000.00 | RM 13,600,000.00 | RM 13,190,106.00 | 97.0% | RM 137,780,756.05 | JANM 2019, pp. 196–197 |
| 91000 | Agensi Penguatkuasaaan Maritim Malaysia (APMM) | RM 4,545,282,100.00 | RM 351,187,459.00 | RM 343,963,294.96 | 97.9% | RM 1,580,930,627.78 | JANM 2019, pp. 196–197 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Development Expenditure (Lampiran 2).