Kementerian Dalam Negeri
A supply (B) vote: the operating spending Parliament voted for this ministry. What it was given and what it spent in 2019, by programme and activity, from the audited Statement of Operating Expenditure.
By programme
Each programme's totals as the statement prints them. Hover a figure for the exact amount, or open an activity below for every line to the sen.
| CodeKod | ProgrammeProgram | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 010000 | Pengurusan Kementerian | RM 275.38 m | RM 313.84 m | RM 286.65 m | 91.3% | RM 27.18 m | JANM 2019, p. 152 |
| 020000 | Keselamatan Dalam Negeri dan Ketenteraman Awam | RM 8.86 bn | RM 8.75 bn | RM 8.55 bn | 97.8% | RM 196.02 m | JANM 2019, p. 153 |
| 030000 | Pengurusan Pendaftaran dan Imigresen | RM 1.12 bn | RM 1.30 bn | RM 1.21 bn | 93.0% | RM 91.14 m | JANM 2019, p. 153 |
| 040000 | Pencegahan, Rawatan dan Pemulihan | RM 1.22 bn | RM 1.22 bn | RM 1.16 bn | 94.9% | RM 62.87 m | JANM 2019, p. 153 |
| 050000 | Program Khusus | RM 1.09 bn | RM 976.27 m | RM 901.21 m | 92.3% | RM 75.06 m | JANM 2019, p. 154 |
Every activity, line by line
Open an activity to see its spending categories exactly as printed, to the sen, each with the page it was read from.
The 2019 statement prints the original budget, the revised budget and actual spending only, with no supplementary or virement columns.
010000Pengurusan Kementerian
010100PengurusanRevised RM 206.06 mSpent RM 187.23 m90.9%
Activity total as printed: revised RM 206,056,214.00, spent RM 187,234,401.78 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 47,135,300.00 | RM 46,539,600.00 | RM 40,547,450.60 | 87.1% | RM 5,992,149.40 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 88,398,600.00 | RM 133,943,360.00 | RM 124,849,181.59 | 93.2% | RM 9,094,178.41 | JANM 2019, p. 152 |
| 30000 | AssetsAset | RM 0.00 | RM 1,719,140.00 | RM 1,400,994.24 | 81.5% | RM 318,145.76 | JANM 2019, p. 152 |
| 40000 | Grants and Fixed ChargesPemberian dan Kenaan Bayaran Tetap | RM 30,203,100.00 | RM 21,451,094.00 | RM 18,148,354.68 | 84.6% | RM 3,302,739.32 | JANM 2019, p. 152 |
| 50000 | Other ExpendituresPerbelanjaan-perbelanjaan Lain | RM 2,000,000.00 | RM 2,403,020.00 | RM 2,288,420.67 | 95.2% | RM 114,599.33 | JANM 2019, p. 152 |
010200Dasar dan OperasiRevised RM 107.78 mSpent RM 99.42 m92.2%
Activity total as printed: revised RM 107,778,970.00, spent RM 99,420,441.84 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 71,970,900.00 | RM 72,566,600.00 | RM 71,384,582.63 | 98.4% | RM 1,182,017.37 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 35,674,900.00 | RM 35,212,370.00 | RM 28,035,859.21 | 79.6% | RM 7,176,510.79 | JANM 2019, p. 152 |
020000Keselamatan Dalam Negeri dan Ketenteraman Awam
020100KepolisanRevised RM 8.16 bnSpent RM 8.00 bn98.0%
Activity total as printed: revised RM 8,164,608,100.00, spent RM 7,998,374,344.13 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 7,235,755,000.00 | RM 7,190,755,000.00 | RM 7,040,846,733.35 | 97.9% | RM 149,908,266.65 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 886,076,100.00 | RM 970,750,600.00 | RM 955,181,084.28 | 98.4% | RM 15,569,515.72 | JANM 2019, p. 152 |
| 30000 | AssetsAset | RM 0.00 | RM 3,102,500.00 | RM 2,346,526.50 | 75.6% | RM 755,973.50 | JANM 2019, p. 152 |
020200KesukarelawanRevised RM 125.81 mSpent RM 122.30 m97.2%
Activity total as printed: revised RM 125,807,000.00, spent RM 122,298,297.69 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 40,749,800.00 | RM 42,538,800.00 | RM 41,795,662.82 | 98.3% | RM 743,137.18 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 83,268,200.00 | RM 82,812,852.00 | RM 80,108,316.17 | 96.7% | RM 2,704,535.83 | JANM 2019, p. 152 |
| 30000 | AssetsAset | RM 0.00 | RM 455,348.00 | RM 394,318.70 | 86.6% | RM 61,029.30 | JANM 2019, p. 152 |
020300Kawalan SempadanRevised RM 3.01 mSpent RM 2.45 m81.4%
Activity total as printed: revised RM 3,013,400.00, spent RM 2,453,043.83 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 818,400.00 | RM 818,400.00 | RM 764,503.48 | 93.4% | RM 53,896.52 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 2,195,000.00 | RM 2,195,000.00 | RM 1,688,540.35 | 76.9% | RM 506,459.65 | JANM 2019, p. 152 |
020400Eastern Sabah Security Command (ESSCOM)Revised RM 25.62 mSpent RM 22.53 m87.9%
Activity total as printed: revised RM 25,624,600.00, spent RM 22,530,730.87 (JANM 2019, p. 152).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 17,058,700.00 | RM 17,058,700.00 | RM 16,356,178.41 | 95.9% | RM 702,521.59 | JANM 2019, p. 152 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 8,565,900.00 | RM 8,565,900.00 | RM 6,174,552.46 | 72.1% | RM 2,391,347.54 | JANM 2019, p. 152 |
020500Penguatkuasaan MaritimRevised RM 426.83 mSpent RM 404.21 m94.7%
Activity total as printed: revised RM 426,830,730.00, spent RM 404,210,149.98 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 468,426,900.00 | RM 296,925,530.00 | RM 280,448,227.79 | 94.5% | RM 16,477,302.21 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 119,195,200.00 | RM 129,845,200.00 | RM 123,702,497.19 | 95.3% | RM 6,142,702.81 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 60,000.00 | RM 59,425.00 | 99.0% | RM 575.00 | JANM 2019, p. 153 |
030000Pengurusan Pendaftaran dan Imigresen
030100Pendaftaran NegaraRevised RM 290.55 mSpent RM 268.66 m92.5%
Activity total as printed: revised RM 290,545,710.00, spent RM 268,655,980.51 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 192,536,000.00 | RM 190,676,000.00 | RM 184,886,761.62 | 97.0% | RM 5,789,238.38 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 89,297,200.00 | RM 97,691,710.00 | RM 81,744,094.93 | 83.7% | RM 15,947,615.07 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 2,178,000.00 | RM 2,025,123.96 | 93.0% | RM 152,876.04 | JANM 2019, p. 153 |
030200Hal Ehwal ImigresenRevised RM 990.85 mSpent RM 922.43 m93.1%
Activity total as printed: revised RM 990,848,900.00, spent RM 922,431,632.90 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 683,302,300.00 | RM 683,302,300.00 | RM 628,105,152.61 | 91.9% | RM 55,197,147.39 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 132,576,600.00 | RM 305,761,438.00 | RM 293,170,314.21 | 95.9% | RM 12,591,123.79 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 1,785,162.00 | RM 1,156,166.08 | 64.8% | RM 628,995.92 | JANM 2019, p. 153 |
030300Pendaftaran PertubuhanRevised RM 23.07 mSpent RM 22.24 m96.4%
Activity total as printed: revised RM 23,070,000.00, spent RM 22,239,428.85 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 13,080,000.00 | RM 13,151,000.00 | RM 13,132,485.80 | 99.9% | RM 18,514.20 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 9,919,000.00 | RM 9,437,664.00 | RM 8,701,043.73 | 92.2% | RM 736,620.27 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 481,336.00 | RM 405,899.32 | 84.3% | RM 75,436.68 | JANM 2019, p. 153 |
040000Pencegahan, Rawatan dan Pemulihan
040100Pembanteras DadahRevised RM 333.36 mSpent RM 313.18 m94.0%
Activity total as printed: revised RM 333,362,679.00, spent RM 313,179,622.96 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 275,150,500.00 | RM 264,150,500.00 | RM 251,319,617.87 | 95.1% | RM 12,830,882.13 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 53,755,000.00 | RM 67,182,384.00 | RM 60,697,096.54 | 90.3% | RM 6,485,287.46 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 2,029,795.00 | RM 1,162,908.55 | 57.3% | RM 866,886.45 | JANM 2019, p. 153 |
040200Kepenjaraan dan KoreksionalRevised RM 891.54 mSpent RM 848.85 m95.2%
Activity total as printed: revised RM 891,543,276.00, spent RM 848,851,797.55 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 770,619,400.00 | RM 741,619,400.00 | RM 709,920,541.96 | 95.7% | RM 31,698,858.04 | JANM 2019, p. 153 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 122,015,400.00 | RM 149,336,128.00 | RM 138,412,273.56 | 92.7% | RM 10,923,854.44 | JANM 2019, p. 153 |
| 30000 | AssetsAset | RM 0.00 | RM 587,748.00 | RM 518,982.03 | 88.3% | RM 68,765.97 | JANM 2019, p. 153 |
050000Program Khusus
050100Bertugas ke Luar NegaraRevised RM 6.10 mSpent RM 4.48 m73.5%
Activity total as printed: revised RM 6,100,000.00, spent RM 4,484,624.57 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 2,100,000.00 | RM 6,100,000.00 | RM 4,484,624.57 | 73.5% | RM 1,615,375.43 | JANM 2019, p. 153 |
050200Pasukan Kawalan KeselamatanRevised RM 10.00 mSpent RM 8.06 m80.6%
Activity total as printed: revised RM 10,000,000.00, spent RM 8,062,379.77 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 7,000,000.00 | RM 10,000,000.00 | RM 8,062,379.77 | 80.6% | RM 1,937,620.23 | JANM 2019, p. 153 |
050300Emolumen Kakitangan KontrakRevised RM 12.01 mSpent RM 9.77 m81.4%
Activity total as printed: revised RM 12,011,000.00, spent RM 9,772,291.27 (JANM 2019, p. 153).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 15,000,000.00 | RM 12,011,000.00 | RM 9,772,291.27 | 81.4% | RM 2,238,708.73 | JANM 2019, p. 153 |
050400Membanteras Pemerdagangan Orang (MAPO)Revised RM 4.00 mSpent RM 1.15 m28.7%
Activity total as printed: revised RM 4,000,000.00, spent RM 1,148,619.90 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 4,000,000.00 | RM 2,419,434.00 | RM 39,403.90 | 1.6% | RM 2,380,030.10 | JANM 2019, p. 154 |
| 30000 | AssetsAset | RM 0.00 | RM 471,350.00 | RM 0.00 | 0.0% | RM 471,350.00 | JANM 2019, p. 154 |
| 40000 | Grants and Fixed ChargesPemberian dan Kenaan Bayaran Tetap | RM 0.00 | RM 1,109,216.00 | RM 1,109,216.00 | 100.0% | RM 0.00 | JANM 2019, p. 154 |
050500Bekalan VaksinRevised RM 3.57 mSpent RM 2.89 m81.1%
Activity total as printed: revised RM 3,565,250.00, spent RM 2,892,240.48 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 5,000,000.00 | RM 3,565,250.00 | RM 2,892,240.48 | 81.1% | RM 673,009.52 | JANM 2019, p. 154 |
050600Material KeselamatanRevised RM 7.35 mSpent RM 5.13 m69.8%
Activity total as printed: revised RM 7,354,571.00, spent RM 5,132,509.00 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 30000 | AssetsAset | RM 10,000,000.00 | RM 7,354,571.00 | RM 5,132,509.00 | 69.8% | RM 2,222,062.00 | JANM 2019, p. 154 |
050700RangsumRevised RM 315.45 mSpent RM 283.44 m89.8%
Activity total as printed: revised RM 315,448,000.00, spent RM 283,435,748.34 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 358,980,000.00 | RM 315,448,000.00 | RM 283,435,748.34 | 89.8% | RM 32,012,251.66 | JANM 2019, p. 154 |
050800SPANCO dan URBRevised RM 158.75 mSpent RM 154.61 m97.4%
Activity total as printed: revised RM 158,749,900.00, spent RM 154,612,391.65 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 166,399,900.00 | RM 158,749,900.00 | RM 154,612,391.65 | 97.4% | RM 4,137,508.35 | JANM 2019, p. 154 |
050900Kad dan Dokumen PengenalanRevised RM 48.50 mSpent RM 48.42 m99.8%
Activity total as printed: revised RM 48,500,000.00, spent RM 48,422,300.00 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 75,000,000.00 | RM 48,500,000.00 | RM 48,422,300.00 | 99.8% | RM 77,700.00 | JANM 2019, p. 154 |
051000Penugasan ESSZONERevised RM 26.64 mSpent RM 26.28 m98.7%
Activity total as printed: revised RM 26,640,000.00, spent RM 26,283,183.71 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 26,640,000.00 | RM 26,640,000.00 | RM 26,283,183.71 | 98.7% | RM 356,816.29 | JANM 2019, p. 154 |
051100MyegRevised RM 34.50 mSpent RM 34.40 m99.7%
Activity total as printed: revised RM 34,500,000.00, spent RM 34,402,444.63 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 35,000,000.00 | RM 34,500,000.00 | RM 34,402,444.63 | 99.7% | RM 97,555.37 | JANM 2019, p. 154 |
051200M-bikeRevised RM 3.00 mSpent RM 2.62 m87.2%
Activity total as printed: revised RM 3,000,000.00, spent RM 2,616,876.50 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 3,000,000.00 | RM 3,000,000.00 | RM 2,616,876.50 | 87.2% | RM 383,123.50 | JANM 2019, p. 154 |
051300I-kadRevised RM 46.50 mSpent RM 39.06 m84.0%
Activity total as printed: revised RM 46,500,000.00, spent RM 39,057,953.93 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 50,000,000.00 | RM 46,500,000.00 | RM 39,057,953.93 | 84.0% | RM 7,442,046.07 | JANM 2019, p. 154 |
051400PDRMnetRevised RM 177.50 mSpent RM 177.47 m100.0%
Activity total as printed: revised RM 177,500,400.00, spent RM 177,470,012.79 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 177,500,400.00 | RM 177,500,400.00 | RM 177,470,012.79 | 100.0% | RM 30,387.21 | JANM 2019, p. 154 |
051500Head To ToeRevised RM 122.41 mSpent RM 103.42 m84.5%
Activity total as printed: revised RM 122,405,000.00, spent RM 103,420,768.71 (JANM 2019, p. 154).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 150,000,000.00 | RM 122,405,000.00 | RM 103,420,768.71 | 84.5% | RM 18,984,231.29 | JANM 2019, p. 154 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Operating Expenditure (Lampiran 1). % used and unspent are worked out from the printed columns.