A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2021, from the audited Statement of Development Expenditure.
Estimate 2021Anggaran
RM 233.71 m
Spent 2021Sebenar
RM 230.30 m
98.5% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.98 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2021Anggaran | Spent 2021Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Institut Kemahiran Belia Negara (IKBN) | RM 166,073,650.00 | RM 25,245,105.00 | RM 25,202,761.80 | 99.8% | RM 25,202,761.80 | JANM 2021, pp. 220–221 |
| 00110 | Program Pembangunan Kemahiran | RM 43,600,000.00 | RM 2,396,765.00 | RM 2,387,004.53 | 99.6% | RM 2,387,004.53 | JANM 2021, pp. 220–221 |
| 00119 | Projek Pembangunan Biro Tatanegara | RM 42,511,300.17 | RM 3,871,500.00 | RM 3,870,077.80 | 100.0% | RM 3,870,077.80 | JANM 2021, pp. 220–221 |
| 00120 | Naik Taraf Institut Latihan Kepimpinan Belia Negara (ILKEB) | RM 53,807,000.00 | RM 2,332,200.00 | RM 2,332,083.92 | 100.0% | RM 2,332,083.92 | JANM 2021, pp. 220–221 |
| 00200 | Naiktaraf Institut Kemahiran Tinggi Belia Negara ( IKTBN) Sepang | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 220–221 | |
| 00300 | Naiktaraf Kompleks Sukan Labuan | RM 20,000,000.00 | RM 9,780.00 | RM 9,693.66 | 99.1% | RM 9,693.66 | JANM 2021, pp. 220–221 |
| 00601 | Naiktaraf Kompleks Belia dan Sukan Negeri-negeri | RM 165,304,326.00 | RM 13,172,800.00 | RM 12,807,928.89 | 97.2% | RM 12,807,928.89 | JANM 2021, pp. 220–221 |
| 00616 | Pusat Latihan Khas | RM 80,577,150.00 | RM 9,890,000.00 | RM 9,890,000.00 | 100.0% | RM 9,890,000.00 | JANM 2021, pp. 220–221 |
| 00906 | Program Pembangunan Ahli Sukan - Skim Kumpulan Ahli Sukan | RM 228,000,000.00 | RM 28,550,000.00 | RM 28,550,000.00 | 100.0% | RM 28,550,000.00 | JANM 2021, pp. 220–221 |
| 01111 | PPP/ PFI - Bayaran Sewaan Bangunan Kementerian Belia Dan Sukan di 4G4, Putrajaya | RM 90,495,000.00 | RM 17,074,250.00 | RM 17,074,184.40 | 100.0% | RM 17,074,184.40 | JANM 2021, pp. 220–221 |
| 00908 | Program Pembangunan Ahli Sukan - Program Latihan/Bakat | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 220–221 | |
| 01800 | Penyediaan Sukan Antarabangsa | RM 370,193,000.00 | RM 50,000,000.00 | RM 50,000,000.00 | 100.0% | RM 50,000,000.00 | JANM 2021, pp. 220–221 |
| 02000 | KRMD Sukan Air dan Udara | RM 29,557,000.00 | RM 2,589,850.00 | RM 2,589,086.69 | 100.0% | RM 2,589,086.69 | JANM 2021, pp. 220–221 |
| 02001 | Kompleks Rakan Muda Daerah (KRMD) | RM 59,000,000.00 | RM 13,623,700.00 | RM 13,389,550.11 | 98.3% | RM 13,389,550.11 | JANM 2021, pp. 220–221 |
| 02004 | Program Pembangunan Rakan Muda | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 220–221 | |
| 02007 | Kompleks Sukan Komuniti | RM 45,404,324.00 | RM 5,678,920.00 | RM 5,324,010.50 | 93.8% | RM 5,324,010.50 | JANM 2021, pp. 220–221 |
| 02100 | Naik Taraf Kompleks Sukan Negara | RM 111,775,000.00 | RM 11,350,000.00 | RM 11,350,000.00 | 100.0% | RM 11,350,000.00 | JANM 2021, pp. 220–221 |
| 02301 | Penyelenggaraan Kompleks dan Kemudahan Sukan Negeri-negeri | RM 46,658,000.00 | RM 7,016,800.00 | RM 7,016,374.87 | 100.0% | RM 7,016,374.87 | JANM 2021, pp. 220–221 |
| 02400 | Gelanggang Sukan | RM 417,946,597.49 | RM 37,717,400.00 | RM 35,320,049.80 | 93.6% | RM 35,320,049.80 | JANM 2021, pp. 220–221 |
| 03000 | Pembangunan Teknologi Maklumat (Pelan Strategik ICT)Note: P.45 – Butiran 03000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2022 telah dimasuk kira sebagai pendahuluan. | RM 500,000.00 | RM 435,700.00 | RM 435,691.80 | 100.0% | RM 435,691.80 | JANM 2021, pp. 220–221 |
| 04007 | Kajian Pembangunan Belia | RM 2,930,000.00 | RM 1,755,000.00 | RM 1,755,000.00 | 100.0% | RM 1,755,000.00 | JANM 2021, pp. 220–221 |
| 05000 | Dana Pembangunan Produk Sukan | RM 2,500,000.00 | RM 1,000,000.00 | RM 1,000,000.00 | 100.0% | RM 1,000,000.00 | JANM 2021, pp. 220–221 |
| 96200 | Program 1M4U | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2021, pp. 220–221 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2021, Statement of Development Expenditure (Lampiran 2).