Estimate 2023Anggaran
RM 119.44 m
Spent 2023Sebenar
RM 118.28 m
99.0% of the estimate
Total cost of projectsKos Keseluruhan
RM 823.04 m
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2023Anggaran | Spent 2023Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00800 | Kajian-kajian Pelancongan | RM 2,600,000.00 | RM 237,000.00 | RM 235,187.98 | 99.2% | RM 464,354.57 | JANM 2023, pp. 204–205 |
| 01100 | Program Penyediaan/Peningkatan Kemudahan Pelancongan | RM 67,835,000.00 | RM 30,364,175.00 | RM 30,019,387.03 | 98.9% | RM 39,699,511.18 | JANM 2023, pp. 204–205 |
| 01400 | Penyelenggaraan Kemudahan/Infrastruktur | RM 30,000,000.00 | RM 0.00 | RM 0.00 | RM 21,715,077.43 | JANM 2023, pp. 204–205 | |
| 01900 | Pembangunan Ecotourism | RM 34,731,000.00 | RM 10,803,410.00 | RM 9,986,075.61 | 92.4% | RM 23,138,637.99 | JANM 2023, pp. 204–205 |
| 02800 | Program Peningkatan Kemudahan Homestay | RM 9,600,000.00 | RM 438,700.00 | RM 438,650.00 | 100.0% | RM 1,049,716.10 | JANM 2023, pp. 204–205 |
| 40600 | Program Pemuliharaan/Pemugaran Tinggalan Sejarah | RM 22,210,000.00 | RM 505,760.00 | RM 505,704.02 | 100.0% | RM 5,399,339.61 | JANM 2023, pp. 204–205 |
| 41400 | Akademi Seni Budaya dan Warisan Kebangsaan (ASWARA) | RM 59,950,000.00 | RM 7,000,000.00 | RM 7,000,000.00 | 100.0% | RM 24,500,000.00 | JANM 2023, pp. 204–205 |
| 41700 | Istana Budaya | RM 73,721,496.00 | RM 1,043,105.00 | RM 1,043,031.39 | 100.0% | RM 7,652,048.80 | JANM 2023, pp. 204–205 |
| 42700 | Menaik Taraf Bangunan-bangunan Arkib Negara Malaysia | RM 75,960,000.00 | RM 0.00 | RM 0.00 | RM 6,908,904.73 | JANM 2023, pp. 204–205 | |
| 43205 | Bangunan Arkib Negara Malaysia Cawangan | RM 30,000,000.00 | RM 0.00 | RM 0.00 | RM 98,510.16 | JANM 2023, pp. 204–205 | |
| 45000 | Pembangunan Teknologi Maklumat | RM 7,965,000.00 | RM 530,800.00 | RM 530,758.25 | 100.0% | RM 3,823,686.65 | JANM 2023, pp. 204–205 |
| 45100 | Ubah Suai dan Menaik Taraf Muzium | RM 40,400,000.00 | RM 0.00 | RM 0.00 | RM 2,448,463.97 | JANM 2023, pp. 204–205 | |
| 49000 | Perbadanan Kemajuan Kraftangan Malaysia | RM 10,300,000.00 | RM 625,000.00 | RM 625,000.00 | 100.0% | RM 1,525,000.00 | JANM 2023, pp. 204–205 |
| 50000 | Jabatan Perpustakaan Negara | RM 20,300,000.00 | RM 0.00 | RM 0.00 | RM 5,883,448.93 | JANM 2023, pp. 204–205 | |
| 80001 | Private Public Partnership/Private Finance (PPP/PFI) | RM 197,465,000.00 | RM 39,493,250.00 | RM 39,493,247.04 | 100.0% | RM 118,479,741.12 | JANM 2023, pp. 204–205 |
| 94000 | Pemasaran dan Promosi | RM 140,000,000.00 | RM 28,400,000.00 | RM 28,400,000.00 | 100.0% | RM 49,541,640.00 | JANM 2023, pp. 204–205 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2023, Statement of Development Expenditure (Lampiran 2).