Estimate 2024Anggaran
RM 2.13 bn
Spent 2024Sebenar
RM 2.12 bn
99.6% of the estimate; RM 23.10 m loan-funded
Total cost of projectsKos Keseluruhan
RM 27.62 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 5.46 bn
Totals as printed, JANM 2024, pp. 194–195

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00010Matlamat Pembangunan MampanRM 44,716,000.00RM 9,871,000.00RM 8,998,485.22
91.2%
RM 10,892,186.85JANM 2024, pp. 194–195
00100Kajian-kajian KemungkinanRM 263,445,772.00RM 30,190,940.00RM 29,698,555.30
98.4%
RM 64,329,401.47JANM 2024, pp. 194–195
00106Penyenggaraan dan PembaikanRM 8,000,000.00RM 6,500,000.00RM 6,440,839.00
99.1%
RM 6,440,839.00JANM 2024, pp. 194–195
00107Pembangunan Iskandar MalaysiaRM 1,734,156,425.00RM 500,000.00RM 500,000.00
100.0%
RM 93,420,000.00JANM 2024, pp. 194–195
00108Program PembangunanRM 1,250,935,000.00RM 361,303,000.00RM 361,032,567.50
99.9%
RM 508,482,567.50JANM 2024, pp. 194–195
00109Program Kerjasama Serantau IMTGT dan BIMP-EAGA dan JDSRM 25,000,000.00RM 5,000,000.00RM 4,844,242.64
96.9%
RM 10,744,690.89JANM 2024, pp. 194–195
00111Malaysian Petroleum Resources CorporationRM 8,000,000.00RM 3,300,000.00RM 3,300,000.00
100.0%
RM 6,900,000.00JANM 2024, pp. 194–195
00113Pembangunan KoridorRM 12,181,461,299.00RM 690,195,059.00RM 690,121,111.49
100.0%
RM 1,847,185,402.74JANM 2024, pp. 194–195
00600Kemajuan Guna Tenaga ManusiaRM 34,000,000.00RM 3,421,691.00RM 1,819,506.32
53.2%
RM 4,808,654.85JANM 2024, pp. 194–195
00614Bangunan PerniagaanRM 4,000,000.00RM 400,000.00RM 400,000.00
100.0%
RM 400,000.00JANM 2024, pp. 194–195
00700GREEN FUNDRM 2,000,000,000.00RM 100,000,000.00RM 100,000,000.00
100.0%
RM 100,000,000.00JANM 2024, pp. 194–195
00900Bantuan Teknik dan PerundingRM 123,600,000.00RM 11,607,000.00RM 11,599,785.36
99.9%
RM 38,500,085.24JANM 2024, pp. 194–195
10000Johor Petroleum Development Corporation (JPDC)RM 11,900,000.00RM 3,100,000.00RM 3,100,000.00
100.0%
RM 4,930,000.00JANM 2024, pp. 194–195
10200Perolehan KomputerRM 131,800,000.00RM 30,300,000.00RM 30,063,571.38
99.2%
RM 44,115,756.92JANM 2024, pp. 194–195
23000Projek Pembangunan Kawasan Sempadan Sabah, Sarawak dan SemenanjungRM 1,100,000,000.00RM 0.00RM 0.00RM 33,105,714.98JANM 2024, pp. 194–195
69000Unit PenerajuRM 1,501,499,950.00RM 0.00RM 0.00RM 77,500,050.00JANM 2024, pp. 194–195
70101Perbadanan Kemajuan Negeri: JohorRM 216,638,900.00RM 4,500,000.00RM 4,500,000.00
100.0%
RM 13,500,000.00JANM 2024, pp. 194–195
70102Perbadanan Kemajuan Negeri: KedahRM 170,227,260.00RM 11,150,000.00RM 11,150,000.00
100.0%
RM 17,519,000.00JANM 2024, pp. 194–195
70103Perbadanan Kemajuan Negeri: KelantanRM 113,746,000.00RM 41,550,000.00RM 41,550,000.00
100.0%
RM 95,050,000.00JANM 2024, pp. 194–195
70104Perbadanan Kemajuan Negeri: MelakaRM 18,451,100.00RM 0.00RM 0.00RM 8,331,312.00JANM 2024, pp. 194–195
70106Perbadanan Kemajuan Negeri: PahangRM 22,714,000.00RM 2,710,000.00RM 2,710,000.00
100.0%
RM 8,300,000.00JANM 2024, pp. 194–195
70109Perbadanan Kemajuan Negeri: PerlisRM 11,150,000.00RM 6,864,200.00RM 6,864,200.00
100.0%
RM 7,364,200.00JANM 2024, pp. 194–195
70111Perbadanan Kemajuan Negeri: TerengganuRM 49,451,654.00RM 12,811,600.00RM 12,811,600.00
100.0%
RM 21,811,600.00JANM 2024, pp. 194–195
70112Perbadanan Kemajuan Negeri: SabahRM 48,843,476.00RM 4,614,000.00RM 4,614,000.00
100.0%
RM 9,614,000.00JANM 2024, pp. 194–195
70113Perbadanan Kemajuan Negeri: SarawakRM 3,774,220.00RM 42,500.00RM 42,500.00
100.0%
RM 42,500.00JANM 2024, pp. 194–195
93500Program/Projek Pembangunan EkonomiRM 6,015,995,702.00RM 613,632,501.00RM 611,563,984.73
99.7%
RM 2,129,471,795.72JANM 2024, pp. 194–195
99000Banci Ekonomi/EKSRM 427,712,450.00RM 155,292,309.00RM 151,768,936.09
97.7%
RM 275,931,042.38JANM 2024, pp. 194–195
99900Program/Projek R&D&C&I RMURM 100,000,000.00RM 18,000,000.00RM 17,981,249.65
99.9%
RM 17,981,249.65JANM 2024, pp. 194–195

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2024, Statement of Development Expenditure (Lampiran 2).