A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2025, from the audited Statement of Development Expenditure.
The same code is printed as Kementerian Hal Ehwal Ekonomi in 2018–2021.
All development votes in 2025 · Operating vote B.15 · P.15 in Budget 2027
Estimate 2025Anggaran
RM 2.25 bn
Spent 2025Sebenar
RM 2.24 bn
99.6% of the estimate; RM 21.23 m loan-funded
Total cost of projectsKos Keseluruhan
RM 36.38 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2025Anggaran | Spent 2025Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00010 | Matlamat Pembangunan Mampan | RM 44,716,000.00 | RM 11,100,900.00 | RM 11,057,814.13 | 99.6% | RM 21,950,000.98 | JANM 2025, pp. 202–203 |
| 00100 | Kajian-kajian Kemungkinan | RM 264,275,772.00 | RM 32,728,800.00 | RM 32,340,668.05 | 98.8% | RM 96,670,069.52 | JANM 2025, pp. 202–203 |
| 00106 | Penyenggaraan dan Pembaikan | RM 12,000,000.00 | RM 3,866,000.00 | RM 3,856,977.47 | 99.8% | RM 10,297,816.47 | JANM 2025, pp. 202–203 |
| 00107 | Pembangunan Iskandar Malaysia | RM 2,017,157,454.00 | RM 61,470,500.00 | RM 61,470,400.00 | 100.0% | RM 154,890,400.00 | JANM 2025, pp. 202–203 |
| 00108 | Program Pembangunan | RM 3,369,935,000.00 | RM 803,752,120.00 | RM 803,752,118.29 | 100.0% | RM 1,312,234,685.79 | JANM 2025, pp. 202–203 |
| 00109 | Program Kerjasama Serantau IMT-GT dan BIMP-EAGA dan JDS | RM 28,000,000.00 | RM 6,748,000.00 | RM 6,747,965.62 | 100.0% | RM 17,492,656.51 | JANM 2025, pp. 202–203 |
| 00110 | Dana Pembangunan Infrastruktur | RM 5,000,000,000.00 | RM 225,000.00 | RM 225,000.00 | 100.0% | RM 225,000.00 | JANM 2025, pp. 202–203 |
| 00111 | Malaysian Petroleum Resources Corporation | RM 8,000,000.00 | RM 150,000.00 | RM 150,000.00 | 100.0% | RM 7,050,000.00 | JANM 2025, pp. 202–203 |
| 00113 | Pembangunan Koridor | RM 13,070,972,299.00 | RM 522,166,900.00 | RM 517,020,049.62 | 99.0% | RM 2,364,205,452.36 | JANM 2025, pp. 202–203 |
| 00600 | Kemajuan Guna Tenaga Manusia | RM 34,218,100.00 | RM 1,657,000.00 | RM 1,656,057.18 | 99.9% | RM 6,464,712.03 | JANM 2025, pp. 202–203 |
| 00614 | Bangunan Perniagaan | RM 4,000,000.00 | RM 2,000,000.00 | RM 2,000,000.00 | 100.0% | RM 2,400,000.00 | JANM 2025, pp. 202–203 |
| 00700 | Pelan Hala Tuju Peralihan Tenaga Negara | RM 2,000,000,000.00 | RM 100,000,000.00 | RM 100,000,000.00 | 100.0% | RM 200,000,000.00 | JANM 2025, pp. 202–203 |
| 00900 | Bantuan Teknik dan Perunding | RM 123,600,000.00 | RM 10,832,700.00 | RM 10,832,687.64 | 100.0% | RM 49,332,772.88 | JANM 2025, pp. 202–203 |
| 10000 | Johor Petroleum Development Corporation (JPDC) | RM 11,900,000.00 | RM 1,806,000.00 | RM 1,799,500.00 | 99.6% | RM 6,729,500.00 | JANM 2025, pp. 202–203 |
| 10200 | Perolehan Komputer | RM 131,800,000.00 | RM 21,937,000.00 | RM 21,419,656.36 | 97.6% | RM 65,535,413.28 | JANM 2025, pp. 202–203 |
| 23000 | Projek Pembangunan Kawasan Sempadan Sabah, Sarawak dan Semenanjung | RM 1,100,000,000.00 | RM 0.00 | RM 0.00 | RM 33,105,714.98 | JANM 2025, pp. 202–203 | |
| 69000 | Unit Peneraju | RM 1,501,499,950.00 | RM 0.00 | RM 0.00 | RM 77,500,050.00 | JANM 2025, pp. 202–203 | |
| 70101 | Perbadanan Kemajuan Negeri: Johor | RM 240,138,900.00 | RM 4,072,200.00 | RM 4,072,200.00 | 100.0% | RM 17,572,200.00 | JANM 2025, pp. 202–203 |
| 70102 | Perbadanan Kemajuan Negeri: Kedah | RM 365,227,260.00 | RM 3,000,000.00 | RM 3,000,000.00 | 100.0% | RM 20,519,000.00 | JANM 2025, pp. 202–203 |
| 70103 | Perbadanan Kemajuan Negeri: Kelantan | RM 113,746,000.00 | RM 0.00 | RM 0.00 | RM 95,050,000.00 | JANM 2025, pp. 202–203 | |
| 70104 | Perbadanan Kemajuan Negeri: Melaka | RM 18,451,100.00 | RM 0.00 | RM 0.00 | RM 8,331,312.00 | JANM 2025, pp. 202–203 | |
| 70106 | Perbadanan Kemajuan Negeri: Pahang | RM 22,714,000.00 | RM 6,384,000.00 | RM 6,384,000.00 | 100.0% | RM 14,684,000.00 | JANM 2025, pp. 202–203 |
| 70109 | Perbadanan Kemajuan Negeri: Perlis | RM 18,193,000.00 | RM 4,688,800.00 | RM 4,688,800.00 | 100.0% | RM 12,053,000.00 | JANM 2025, pp. 202–203 |
| 70111 | Perbadanan Kemajuan Negeri: Terengganu | RM 50,205,655.00 | RM 8,540,000.00 | RM 8,540,000.00 | 100.0% | RM 30,351,600.00 | JANM 2025, pp. 202–203 |
| 70112 | Perbadanan Kemajuan Negeri: Sabah | RM 52,643,476.00 | RM 5,295,782.00 | RM 5,295,700.00 | 100.0% | RM 14,909,700.00 | JANM 2025, pp. 202–203 |
| 70113 | Perbadanan Kemajuan Negeri: Sarawak | RM 3,774,221.00 | RM 0.00 | RM 0.00 | RM 42,500.00 | JANM 2025, pp. 202–203 | |
| 93500 | Program/Projek Pembangunan Ekonomi | RM 6,137,995,703.00 | RM 543,926,880.00 | RM 542,555,021.31 | 99.8% | RM 2,672,026,817.03 | JANM 2025, pp. 202–203 |
| 99000 | Banci Ekonomi/EKS | RM 532,712,450.00 | RM 73,070,038.00 | RM 72,081,912.95 | 98.7% | RM 348,012,955.33 | JANM 2025, pp. 202–203 |
| 99900 | Program/Projek R&D&C&I RMU | RM 100,000,000.00 | RM 20,614,000.00 | RM 20,613,851.15 | 100.0% | RM 38,595,100.80 | JANM 2025, pp. 202–203 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).