Kementerian Pertahanan
A development (P) vote in Budget 2025: what the Ministry of Finance's budget book sets aside for it in 2025, beside the 2024 budget and what it spent in the two years before.
Actual 2022Perbelanjaan Sebenar
RM 4.75 bn
Actual 2023Perbelanjaan Sebenar
RM 6.04 bn
Budget 2024Anggaran Asal
RM 7.05 bn
Every project
Each project as the book prints it, in whole ringgit.
| CodeKod | ProjectTajuk | Total costJumlah Anggaran Harga Projek | Revised budget 2024Anggaran Dipinda | Budget 2025Anggaran | SourceSumber |
|---|---|---|---|---|---|
| Tentera Darat | |||||
| 00100 | Pembinaan (Tentera Darat) | RM 2,070,021,696 | RM 182,150,100 | RM 217,549,800 | MOF Budget 2025, p. 461 |
| 00200 | Kelengkapan (Tentera Darat) | RM 7,826,298,500 | RM 521,860,000 | RM 980,144,400 | MOF Budget 2025, p. 461 |
| Tentera Laut | |||||
| 00300 | Pembinaan (Tentera Laut) | RM 697,800,000 | RM 119,900,000 | RM 149,915,000 | MOF Budget 2025, p. 461 |
| 00400 | Kelengkapan (Tentera Laut) | RM 19,900,525,894 | RM 1,894,952,700 | RM 2,105,518,600 | MOF Budget 2025, p. 461 |
| Tentera Udara | |||||
| 00500 | Pembinaan (Tentera Udara) | RM 466,890,750 | RM 23,910,000 | RM 64,402,600 | MOF Budget 2025, p. 461 |
| 00600 | Kelengkapan (Tentera Udara) | RM 21,011,095,000 | RM 2,026,259,690 | RM 2,215,568,600 | MOF Budget 2025, p. 461 |
| Tiga Perkhidmatan | |||||
| 00700 | Pembinaan (Tiga Perkhidmatan) | RM 702,836,366 | RM 48,000,000 | RM 67,386,400 | MOF Budget 2025, p. 461 |
| 00800 | Kelengkapan (Tiga Perkhidmatan) | RM 662,324,100 | RM 25,000,000 | RM 596,479,600 | MOF Budget 2025, p. 461 |
| Lain-lain | |||||
| 00900 | Pembinaan (Awam) | RM 374,325,530 | RM 51,143,400 | RM 53,402,500 | MOF Budget 2025, p. 461 |
| 01000 | Kelengkapan (Awam) | RM 8,000,000 | RM 0 | RM 4,000,000 | MOF Budget 2025, p. 461 |
| 01200 | Penyelidikan dan Pembangunan Pertahanan (Lain-lain) | RM 169,595,000 | RM 35,700,000 | RM 58,892,000 | MOF Budget 2025, p. 461 |
| 08400 | Perumahan Angkatan Tentera Malaysia | RM 3,638,106,720 | RM 505,464,900 | RM 698,327,400 | MOF Budget 2025, p. 462 |
| 02000 | PPP/PFI | RM 306,158,200 | RM 16,000,000 | RM 230,445,500 | MOF Budget 2025, p. 462 |
| 04000 | Program Latihan Khidmat Negara | RM 340,951,800 | RM 0 | RM 50,000,000 | MOF Budget 2025, p. 462 |
Vote figures as printed in the budget summary. Activities and projects are listed as the 2025 budget defines them; codes are reused across years for different activities, so they are not matched to past spending line by line. Source: Kementerian Kewangan, Anggaran Perbelanjaan Persekutuan 2025.