Kementerian Pembangunan Wanita, Keluarga dan Masyarakat
A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2016, from the audited Statement of Development Expenditure.
Estimate 2016Anggaran
RM 94.18 m
Spent 2016Sebenar
RM 82.63 m
87.7% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.74 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2016Anggaran | Spent 2016Sebenar | % usedPrestasi | RMKe-11 to dateSebenar RMKe-11 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00300 | Lembaga Penduduk dan Pembangunan Keluarga Negara (LPPKN) | RM 42,300,000.00 | RM 7,300,000.00 | RM 5,300,000.00 | 72.6% | RM 5,300,000.00 | JANM 2016, pp. 240–241 |
| 00502 | Rumah Pesakit MelaratNote: P.48 Butiran 00502 dan 00701 - Peruntukan sebanyak RM10 bagi setiap butiran yang diambil kira sebagai pendahuluan akan dibentangkan dalam sesi Parlimen 2017. | RM 54,531,900.00 | RM 602,010.00 | RM 288,125.14 | 47.9% | RM 288,125.14 | JANM 2016, pp. 240–241 |
| 00503 | Rumah Seri Kenangan | RM 77,500,000.00 | RM 10,550,000.00 | RM 9,660,438.14 | 91.6% | RM 9,660,438.14 | JANM 2016, pp. 240–241 |
| 00504 | Rumah Kanak-kanak | RM 20,000,000.00 | RM 416,447.00 | RM 0.00 | 0.0% | RM 0.00 | JANM 2016, pp. 240–241 |
| 00601 | Bengkel Daya Klang Selangor (Fasa II) | RM 2,500,000.00 | RM 43,000.00 | RM 42,991.77 | 100.0% | RM 42,991.77 | JANM 2016, pp. 240–241 |
| 00602 | Taman Sinar Harapan | RM 68,475,472.00 | RM 11,400,000.00 | RM 11,365,010.31 | 99.7% | RM 11,365,010.31 | JANM 2016, pp. 240–241 |
| 00701 | Sekolah Tunas BaktiNote: P.48 Butiran 00502 dan 00701 - Peruntukan sebanyak RM10 bagi setiap butiran yang diambil kira sebagai pendahuluan akan dibentangkan dalam sesi Parlimen 2017. | RM 40,300,000.00 | RM 12,500,010.00 | RM 12,284,444.44 | 98.3% | RM 12,284,444.44 | JANM 2016, pp. 240–241 |
| 00702 | Asrama Akhlak | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 00703 | Taman Seri Puteri | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 00704 | Pembinaan/Pembesaran Institut Kebajikan Sedia Ada | RM 5,000,000.00 | RM 3,000,000.00 | RM 2,316,505.03 | 77.2% | RM 2,316,505.03 | JANM 2016, pp. 240–241 |
| 00705 | Kuarters Institusi Kebajikan | RM 243,587,250.00 | RM 27,500,000.00 | RM 26,828,754.88 | 97.6% | RM 26,828,754.88 | JANM 2016, pp. 240–241 |
| 00800 | Pejabat Kebajikan Masyarakat Negeri / Daerah | RM 5,900,000.00 | RM 1,500,000.00 | RM 1,042,642.40 | 69.5% | RM 1,042,642.40 | JANM 2016, pp. 240–241 |
| 00900 | Institusi Sosial Malaysia | RM 2,260,000.00 | RM 1,130,000.00 | RM 1,018,869.88 | 90.2% | RM 1,018,869.88 | JANM 2016, pp. 240–241 |
| 01001 | Pusat Aktiviti Warga Emas | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 01100 | Penyelidikan Sains Sosial | RM 7,760,000.00 | RM 3,855,000.00 | RM 3,272,605.46 | 84.9% | RM 3,272,605.46 | JANM 2016, pp. 240–241 |
| 01200 | Pengkomputeran KPWKM | RM 20,350,000.00 | RM 7,850,000.00 | RM 4,858,037.64 | 61.9% | RM 4,858,037.64 | JANM 2016, pp. 240–241 |
| 01300 | Kompleks Penyayang | RM 58,000,000.00 | RM 250,625.00 | RM 188,189.87 | 75.1% | RM 188,189.87 | JANM 2016, pp. 240–241 |
| 01500 | Bayaran Pengambilan Tanah | RM 4,453,553.00 | RM 4,453,553.00 | RM 2,572,328.00 | 57.8% | RM 2,572,328.00 | JANM 2016, pp. 240–241 |
| 01700 | Kompleks Perlindungan Sementara | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 01800 | Pusat Khidmat Setempat OKU | RM 1,000,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 01900 | Depoh Simpanan Keperluan Mangsa Bencana | RM 30,000,000.00 | RM 181,000.00 | RM 30,934.65 | 17.1% | RM 30,934.65 | JANM 2016, pp. 240–241 |
| 02000 | Rumah Perlindungan Khas | RM 9,500,000.00 | RM 1,645,000.00 | RM 1,559,269.00 | 94.8% | RM 1,559,269.00 | JANM 2016, pp. 240–241 |
| 03000 | NKRA 4 - MENINGKATKAN TARAF HIDUP RAKYAT (LOW INCOME HOUSEHOLD) | RM 0.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 | |
| 03100 | Naiktaraf Bangunan KPWKM di Lot 4G11, Putrajaya | RM 1,051,092,254.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2016, pp. 240–241 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2016, Statement of Development Expenditure (Lampiran 2).