A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2018, from the audited Statement of Development Expenditure.

Estimate 2018Anggaran
RM 139.77 m
Spent 2018Sebenar
RM 138.47 m
99.1% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.04 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 365.49 m
Totals as printed, JANM 2018, pp. 234–235

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2018AnggaranSpent 2018Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00300Lembaga Penduduk dan Pembangunan Keluarga NegaraRM 37,400,000.00RM 4,300,000.00RM 4,300,000.00
100.0%
RM 14,518,000.00JANM 2018, pp. 234–235
00502Rumah Pesakit MelaratRM 54,531,900.00RM 6,619,800.00RM 6,619,796.32
100.0%
RM 14,549,105.88JANM 2018, pp. 234–235
00503Rumah Seri KenanganRM 77,500,000.00RM 7,226,210.00RM 7,226,174.05
100.0%
RM 34,996,107.25JANM 2018, pp. 234–235
00504Rumah Kanak-kanakRM 15,000,000.00RM 2,091,000.00RM 1,981,990.00
94.8%
RM 2,201,637.00JANM 2018, pp. 234–235
00601Bengkel Daya Klang, Selangor (Fasa 2)RM 2,500,000.00RM 0.00RM 0.00RM 42,991.77JANM 2018, pp. 234–235
00602Taman Sinar HarapanRM 68,475,472.00RM 411,800.00RM 410,054.30
99.6%
RM 15,084,732.58JANM 2018, pp. 234–235
00701Sekolah Tunas BaktiRM 40,300,000.00RM 3,581,367.00RM 3,581,346.33
100.0%
RM 30,135,840.79JANM 2018, pp. 234–235
00704Pembaikan/Pembesaran Institut Kebajikan Sedia AdaRM 105,000,000.00RM 0.00RM 0.00RM 4,899,576.46JANM 2018, pp. 234–235
00705Kuarters Institusi KebajikanRM 243,587,250.00RM 35,934,900.00RM 35,829,533.22
99.7%
RM 80,115,028.90JANM 2018, pp. 234–235
00800Pejabat Kebajikan Masyarakat Negeri / DaerahRM 5,900,000.00RM 0.00RM 0.00RM 1,042,642.40JANM 2018, pp. 234–235
00900Institusi Sosial MalaysiaRM 2,260,000.00RM 0.00RM 0.00RM 1,812,968.88JANM 2018, pp. 234–235
01001Pusat Jagaan Harian Warga TuaRM 17,000,000.00RM 2,868,700.00RM 2,751,777.19
95.9%
RM 2,751,777.19JANM 2018, pp. 234–235
01100Penyelidikan Sains SosialRM 17,760,000.00RM 2,285,500.00RM 2,261,656.66
99.0%
RM 8,826,625.90JANM 2018, pp. 234–235
01200Pengkomputeran KPWKMRM 20,350,000.00RM 2,227,000.00RM 2,025,836.36
91.0%
RM 13,910,188.28JANM 2018, pp. 234–235
01300Kompleks PenyayangRM 74,173,410.00RM 23.00RM 0.00
0.0%
RM 202,016.87JANM 2018, pp. 234–235
01500Bayaran Pengambilan TanahRM 4,757,231.00RM 0.00RM 0.00RM 2,876,006.00JANM 2018, pp. 234–235
01800Pusat Khidmat Setempat OKURM 1,000,000.00RM 0.00RM 0.00RM 17,920.76JANM 2018, pp. 234–235
01900Depoh Simpanan Keperluan Mangsa BencanaRM 30,000,000.00RM 9,356,500.00RM 9,355,874.03
100.0%
RM 10,996,169.71JANM 2018, pp. 234–235
02000Rumah Perlindungan KhasRM 9,500,000.00RM 280,000.00RM 261,397.60
93.4%
RM 3,011,826.68JANM 2018, pp. 234–235
03100Naiktaraf Bangunan KPWKM di Lot 4G11, PutrajayaRM 211,188,400.00RM 62,584,600.00RM 61,863,867.01
98.8%
RM 123,499,630.43JANM 2018, pp. 234–235

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2018, Statement of Development Expenditure (Lampiran 2).