Skip to content

Kementerian Sains, Teknologi dan Inovasi

A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2025, from the audited Statement of Development Expenditure.

The same code is printed as Kementerian Tenaga, Sains, Teknologi, Alam Sekitar dan Perubahan Iklim in 2018–2019.

All development votes in 2025 · Operating vote B.30 · P.30 in Budget 2027

Estimate 2025Anggaran
RM 488.52 m
Spent 2025Sebenar
RM 468.40 m
95.9% of the estimate
Total cost of projectsKos Keseluruhan
RM 3.06 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 2.10 bn
Totals as printed, JANM 2025, pp. 220–221

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Pembangunan Perkhidmatan StiRM 130.45 mRM 130.45 m
100.0%
RM 488.64 mJANM 2025, pp. 218–219
Penyelidikan StiRM 139.41 mRM 139.41 m
100.0%
RM 514.87 mJANM 2025, pp. 218–219
Pengkomersialan StiRM 218.66 mRM 198.53 m
90.8%
RM 1.10 bnJANM 2025, pp. 220–221

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Pembangunan Perkhidmatan Sti9 projectsEstimate RM 130.45 m · Spent RM 130.45 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00200Jabatan Kimia MalaysiaRM 186,132,300.00RM 20,019,800.00RM 20,019,032.95
100.0%
RM 115,413,887.16JANM 2025, pp. 218–219
00500Baik Pulih dan Penyelenggaraan Bangunan dan PeralatanRM 90,000,000.00RM 49,931,400.00RM 49,931,376.81
100.0%
RM 89,873,162.92JANM 2025, pp. 218–219
00602PlanetariumRM 40,915,976.00RM 1,514,300.00RM 1,514,220.00
100.0%
RM 6,844,879.20JANM 2025, pp. 218–219
00603Agensi Angkasa Malaysia (MYSA)RM 97,640,000.00RM 29,836,200.00RM 29,836,110.90
100.0%
RM 80,493,696.57JANM 2025, pp. 218–219
00604Pusat Sains Negara (PSN)RM 66,400,000.00RM 16,367,083.00RM 16,366,987.88
100.0%
RM 39,797,734.97JANM 2025, pp. 218–219
00900Agensi Nuklear MalaysiaRM 92,915,041.00RM 8,052,400.00RM 8,052,226.86
100.0%
RM 59,366,443.35JANM 2025, pp. 218–219
01000Jabatan Tenaga AtomRM 24,171,000.00RM 3,394,200.00RM 3,394,114.40
100.0%
RM 15,125,524.48JANM 2025, pp. 218–219
97000PPP/PFIRM 72,820,000.00RM 0.00RM 0.00RM 72,819,845.01JANM 2025, pp. 218–219
98000Akademi Sains Malaysia (ASM)RM 8,900,000.00RM 1,335,000.00RM 1,335,000.00
100.0%
RM 8,900,000.00JANM 2025, pp. 218–219
Penyelidikan Sti4 projectsEstimate RM 139.41 m · Spent RM 139.41 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00605Institut Bioteknologi Kebangsaan Malaysia (NIBM)RM 101,855,000.00RM 10,742,700.00RM 10,742,700.00
100.0%
RM 84,318,700.00JANM 2025, pp. 218–219
00608Pusat Maklumat Sains dan Teknologi Malaysia (MASTIC)RM 10,400,000.00RM 0.00RM 0.00RM 2,626,147.32JANM 2025, pp. 218–219
00800Program Penyelidikan dan Pembangunan (R&D)RM 720,920,000.00RM 121,946,517.00RM 121,946,517.00
100.0%
RM 401,614,428.95JANM 2025, pp. 218–219
03700Yayasan Inovasi MalaysiaRM 32,074,000.00RM 6,725,000.00RM 6,725,000.00
100.0%
RM 26,310,000.00JANM 2025, pp. 218–219
Pengkomersialan Sti10 projectsEstimate RM 218.66 m · Spent RM 198.53 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
01100MIMOS Bhd.RM 171,760,000.00RM 53,659,000.00RM 53,659,000.00
100.0%
RM 148,716,000.00JANM 2025, pp. 218–219
01300Technology Park Malaysia (TPM)RM 49,253,611.00RM 0.00RM 0.00RM 25,500,000.00JANM 2025, pp. 218–219
03600Program Pengkomersialan Nano TeknologiRM 109,075,000.00RM 9,500,000.00RM 9,500,000.00
100.0%
RM 96,139,313.02JANM 2025, pp. 218–219
03900Pusat Nanoteknologi Kebangsaan (NNC)RM 9,075,000.00RM 0.00RM 0.00RM 2,820,173.05JANM 2025, pp. 218–219
08000Malaysian Global Innovation and Creativity CentreRM 37,400,000.00RM 0.00RM 0.00RM 14,500,000.00JANM 2025, pp. 220–221
09000Pelbagai Suntikan EkuitiRM 515,000,000.00RM 25,750,000.00RM 19,625,000.00
76.2%
RM 340,776,700.00JANM 2025, pp. 220–221
18000Malaysian Research Accelerator for Technology & Innovation (MRANTI)RM 106,653,612.00RM 3,750,000.00RM 3,750,000.00
100.0%
RM 56,719,600.00JANM 2025, pp. 220–221
40009Malaysian Bioeconomy Development CorporationRM 85,000,000.00RM 12,000,000.00RM 10,000,000.00
83.3%
RM 36,897,300.00JANM 2025, pp. 220–221
83000MIGHTRM 250,000,000.00RM 66,000,000.00RM 66,000,000.00
100.0%
RM 234,700,000.00JANM 2025, pp. 220–221
94000Malaysia Debt Ventures Berhad (MDV)RM 178,000,000.00RM 48,000,000.00RM 36,000,000.00
75.0%
RM 140,000,000.00JANM 2025, pp. 220–221
Projects printed without a group subtotal1 project

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00400Bahagian Teknologi Strategik dan Aplikasi S&TRM 1,100,000.00RM 0.00RM 0.00RM 962,350.00JANM 2025, pp. 220–221

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).