Skip to content

Kementerian Air, Tanah dan Sumber Asli

A supply (B) vote: the operating spending Parliament voted for this ministry. What it was given and what it spent in 2019, by programme and activity, from the audited Statement of Operating Expenditure.

The same code is printed as Kementerian Sumber Asli dan Alam Sekitar in 2016–2017, Kementerian Tenaga dan Sumber Asli in 2020–2022, Kementerian Sumber Asli, Alam Sekitar dan Perubahan Iklim in 2023 and Kementerian Sumber Asli dan Kelestarian Alam in 2024–2025.

All operating votes in 2019 · Development vote P.23 · B.23 in Budget 2027

Original budgetAsal
RM 1.17 bn
Revised budgetJumlah
RM 1.17 bn
SpentSebenar
RM 1.23 bn
105.0% of the revised budget
UnspentVarian
-RM 58.24 m
Totals as printed, JANM 2019, p. 110

By programme

Each programme's totals as the statement prints them. Hover a figure for the exact amount, or open an activity below for every line to the sen.

CodeKodProgrammeProgramOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
010000Pengurusan KementerianRM 208.72 mRM 206.34 mRM 206.33 m
100.0%
RM 3,754.03JANM 2019, p. 107
020000Pengurusan Air, Geologi dan TanahRM 511.73 mRM 498.98 mRM 498.97 m
100.0%
RM 11,413.11JANM 2019, p. 108
030000Pengurusan Hutan dan BiodiversitiRM 169.28 mRM 189.52 mRM 209.82 m
110.7%
-RM 20.31 mJANM 2019, p. 109
040000Pembangunan AirRM 63.19 mRM 59.11 mRM 59.10 m
100.0%
RM 16,228.78JANM 2019, p. 109
050000Program KhususRM 219.58 mRM 218.56 mRM 22.21 m
10.2%
RM 196.35 mJANM 2019, p. 110

Every activity, line by line

Open an activity to see its spending categories exactly as printed, to the sen, each with the page it was read from.

The 2019 statement prints the original budget, the revised budget and actual spending only, with no supplementary or virement columns.

010000Pengurusan Kementerian

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
010100Khidmat PengurusanRevised RM 191.42 mSpent RM 191.42 m
100.0%

Activity total as printed: revised RM 191,423,465.00, spent RM 191,421,381.30 (JANM 2019, p. 107).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 20,035,900.00RM 22,051,037.00RM 22,050,856.09
100.0%
RM 180.91JANM 2019, p. 107
20000Supplies and ServicesPerkhidmatan dan BekalanRM 22,192,600.00RM 22,659,172.00RM 22,658,206.34
100.0%
RM 965.66JANM 2019, p. 107
30000AssetsAsetRM 100,000.00RM 211,524.00RM 211,317.40
99.9%
RM 206.60JANM 2019, p. 107
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 150,076,200.00RM 146,501,732.00RM 146,501,001.47
100.0%
RM 730.53JANM 2019, p. 107
010200Pengurusan Sumber AsliRevised RM 14.91 mSpent RM 14.91 m
100.0%

Activity total as printed: revised RM 14,913,203.00, spent RM 14,911,532.67 (JANM 2019, p. 107).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 12,631,800.00RM 12,595,300.00RM 12,595,059.44
100.0%
RM 240.56JANM 2019, p. 107
20000Supplies and ServicesPerkhidmatan dan BekalanRM 2,975,500.00RM 1,419,003.00RM 1,418,084.27
99.9%
RM 918.73JANM 2019, p. 107
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 712,900.00RM 898,900.00RM 898,388.96
99.9%
RM 511.04JANM 2019, p. 107

020000Pengurusan Air, Geologi dan Tanah

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
020100Jabatan Ketua Pengarah Tanah dan Galian Persekutuan (JKPTG)Revised RM 60.53 mSpent RM 60.53 m
100.0%

Activity total as printed: revised RM 60,530,129.00, spent RM 60,527,238.55 (JANM 2019, p. 107).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 56,001,800.00RM 49,101,659.00RM 49,101,286.72
100.0%
RM 372.28JANM 2019, p. 107
20000Supplies and ServicesPerkhidmatan dan BekalanRM 11,005,000.00RM 10,670,000.00RM 10,668,922.03
100.0%
RM 1,077.97JANM 2019, p. 107
30000AssetsAsetRM 890,800.00RM 601,470.00RM 600,977.10
99.9%
RM 492.90JANM 2019, p. 107
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 115,000.00RM 157,000.00RM 156,052.70
99.4%
RM 947.30JANM 2019, p. 107
020200Ukur dan Pemetaan MalaysiaRevised RM 246.76 mSpent RM 246.76 m
100.0%

Activity total as printed: revised RM 246,760,600.00, spent RM 246,757,284.86 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 201,152,400.00RM 198,551,900.00RM 198,551,644.88
100.0%
RM 255.12JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 47,684,100.00RM 47,780,700.00RM 47,780,543.54
100.0%
RM 156.46JANM 2019, p. 108
30000AssetsAsetRM 1,300,000.00RM 371,000.00RM 370,754.00
99.9%
RM 246.00JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 41,000.00RM 56,000.00RM 54,342.44
97.0%
RM 1,657.56JANM 2019, p. 108
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 1,000.00RM 1,000.00RM 0.00
0.0%
RM 1,000.00JANM 2019, p. 108
020300Mineral dan GeosainsRevised RM 64.42 mSpent RM 64.42 m
100.0%

Activity total as printed: revised RM 64,418,611.00, spent RM 64,418,096.33 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 56,317,700.00RM 52,665,700.00RM 52,665,668.92
100.0%
RM 31.08JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 10,292,100.00RM 10,196,600.00RM 10,196,133.65
100.0%
RM 466.35JANM 2019, p. 108
30000AssetsAsetRM 300,000.00RM 1,116,311.00RM 1,116,295.32
100.0%
RM 15.68JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 440,000.00RM 440,000.00RM 439,998.44
100.0%
RM 1.56JANM 2019, p. 108
020400Pengaliran dan SaliranRevised RM 101.60 mSpent RM 101.60 m
100.0%

Activity total as printed: revised RM 101,599,330.00, spent RM 101,597,237.88 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 72,017,000.00RM 73,375,000.00RM 73,374,631.01
100.0%
RM 368.99JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 25,258,000.00RM 25,643,000.00RM 25,641,944.18
100.0%
RM 1,055.82JANM 2019, p. 108
30000AssetsAsetRM 3,100,000.00RM 2,571,330.00RM 2,571,007.28
100.0%
RM 322.72JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 15,000.00RM 10,000.00RM 9,655.41
96.5%
RM 344.59JANM 2019, p. 108
020500Institut Tanah dan Ukur Negara (INSTUN)Revised RM 12.39 mSpent RM 12.39 m
100.0%

Activity total as printed: revised RM 12,391,891.00, spent RM 12,390,161.13 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 7,760,800.00RM 7,860,391.00RM 7,859,406.05
100.0%
RM 984.95JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 4,255,200.00RM 4,225,200.00RM 4,224,500.68
100.0%
RM 699.32JANM 2019, p. 108
30000AssetsAsetRM 300,000.00RM 302,000.00RM 301,954.40
100.0%
RM 45.60JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 4,300.00RM 4,300.00RM 4,300.00
100.0%
RM 0.00JANM 2019, p. 108
020600Institut Penyelidikan Hidraulik Kebangsaan Malaysia (NAHRIM)Revised RM 13.28 mSpent RM 13.28 m
100.0%

Activity total as printed: revised RM 13,282,100.00, spent RM 13,281,229.14 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 10,742,400.00RM 10,574,400.00RM 10,574,208.60
100.0%
RM 191.40JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 2,510,000.00RM 2,498,900.00RM 2,498,353.37
100.0%
RM 546.63JANM 2019, p. 108
30000AssetsAsetRM 200,000.00RM 177,500.00RM 177,458.36
100.0%
RM 41.64JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 23,900.00RM 31,300.00RM 31,208.81
99.7%
RM 91.19JANM 2019, p. 108

030000Pengurusan Hutan dan Biodiversiti

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
030100Perhutanan Semenanjung MalaysiaRevised RM 49.21 mSpent RM 69.52 m
141.3%

Activity total as printed: revised RM 49,212,035.00, spent RM 69,519,627.01 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 26,932,700.00RM 23,688,200.00RM 23,687,333.89
100.0%
RM 866.11JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 4,142,100.00RM 5,145,610.00RM 5,145,168.29
100.0%
RM 441.71JANM 2019, p. 108
30000AssetsAsetRM 0.00RM 19,735,025.00RM 40,045,024.04
202.9%
-RM 20,309,999.04JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 829,000.00RM 642,000.00RM 641,560.79
99.9%
RM 439.21JANM 2019, p. 108
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 1,200.00RM 1,200.00RM 540.00
45.0%
RM 660.00JANM 2019, p. 108
030200Perlindungan Hidupan Liar dan Taman NegaraRevised RM 80.37 mSpent RM 80.37 m
100.0%

Activity total as printed: revised RM 80,368,334.00, spent RM 80,367,327.48 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 62,022,200.00RM 60,689,225.00RM 60,688,836.82
100.0%
RM 388.18JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 14,721,200.00RM 18,388,309.00RM 18,387,991.31
100.0%
RM 317.69JANM 2019, p. 108
30000AssetsAsetRM 200,000.00RM 165,332.00RM 165,332.00
100.0%
RM 0.00JANM 2019, p. 108
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 520,000.00RM 1,125,468.00RM 1,125,167.35
100.0%
RM 300.65JANM 2019, p. 108
030300BiokeselamatanRevised RM 1.91 mSpent RM 1.91 m
100.0%

Activity total as printed: revised RM 1,905,223.00, spent RM 1,905,065.17 (JANM 2019, p. 108).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 1,688,400.00RM 1,710,623.00RM 1,710,582.70
100.0%
RM 40.30JANM 2019, p. 108
20000Supplies and ServicesPerkhidmatan dan BekalanRM 192,700.00RM 194,600.00RM 194,482.47
99.9%
RM 117.53JANM 2019, p. 108
030400Institut Penyelidikan Perhutanan Malaysia (FRIM)Revised RM 58.03 mSpent RM 58.03 m
100.0%

Activity total as printed: revised RM 58,031,100.00, spent RM 58,031,100.00 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 58,031,100.00RM 58,031,100.00RM 58,031,100.00
100.0%
RM 0.00JANM 2019, p. 109

040000Pembangunan Air

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
040100Pengurusan AirRevised RM 2.48 mSpent RM 2.48 m
99.8%

Activity total as printed: revised RM 2,482,040.00, spent RM 2,476,126.27 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 4,628,600.00RM 2,271,740.00RM 2,270,997.74
100.0%
RM 742.26JANM 2019, p. 109
20000Supplies and ServicesPerkhidmatan dan BekalanRM 185,300.00RM 110,300.00RM 109,070.69
98.9%
RM 1,229.31JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 100,000.00RM 100,000.00RM 96,057.84
96.1%
RM 3,942.16JANM 2019, p. 109
040200Bekalan Air Ibu PejabatRevised RM 6.57 mSpent RM 6.57 m
100.0%

Activity total as printed: revised RM 6,570,889.00, spent RM 6,568,997.47 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 6,689,000.00RM 5,783,000.00RM 5,782,791.01
100.0%
RM 208.99JANM 2019, p. 109
20000Supplies and ServicesPerkhidmatan dan BekalanRM 1,479,200.00RM 783,889.00RM 782,774.82
99.9%
RM 1,114.18JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 5,000.00RM 3,000.00RM 2,469.64
82.3%
RM 530.36JANM 2019, p. 109
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 0.00RM 1,000.00RM 962.00
96.2%
RM 38.00JANM 2019, p. 109
040300Bekalan Air Wilayah Persekutuan LabuanRevised RM 33.47 mSpent RM 33.47 m
100.0%

Activity total as printed: revised RM 33,471,890.00, spent RM 33,468,471.47 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 6,215,400.00RM 5,682,400.00RM 5,681,366.01
100.0%
RM 1,033.99JANM 2019, p. 109
20000Supplies and ServicesPerkhidmatan dan BekalanRM 25,450,000.00RM 27,718,490.00RM 27,717,115.46
100.0%
RM 1,374.54JANM 2019, p. 109
30000AssetsAsetRM 100,000.00RM 21,000.00RM 19,990.00
95.2%
RM 1,010.00JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 50,000.00RM 50,000.00RM 50,000.00
100.0%
RM 0.00JANM 2019, p. 109
040400Perkhidmatan PembentunganRevised RM 16.59 mSpent RM 16.58 m
100.0%

Activity total as printed: revised RM 16,588,300.00, spent RM 16,583,295.01 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
10000EmolumentsEmolumenRM 11,533,200.00RM 11,177,200.00RM 11,175,817.78
100.0%
RM 1,382.22JANM 2019, p. 109
20000Supplies and ServicesPerkhidmatan dan BekalanRM 6,753,100.00RM 5,408,100.00RM 5,407,477.23
100.0%
RM 622.77JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 3,000.00RM 3,000.00RM 0.00
0.0%
RM 3,000.00JANM 2019, p. 109

050000Program Khusus

ActivityAktivitiRevised budgetJumlahSpentSebenar% usedPrestasi
050100Bertugas ke Luar NegaraRevised RM 2.08 mSpent RM 2.07 m
100.0%

Activity total as printed: revised RM 2,075,100.00, spent RM 2,074,231.61 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
20000Supplies and ServicesPerkhidmatan dan BekalanRM 2,323,600.00RM 2,025,100.00RM 2,024,231.61
100.0%
RM 868.39JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 0.00RM 50,000.00RM 50,000.00
100.0%
RM 0.00JANM 2019, p. 109
050200Emolumen Kakitangan KontrakRevised RM 516,600.00Spent RM 516,222.20
99.9%

Activity total as printed: revised RM 516,600.00, spent RM 516,222.20 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
20000Supplies and ServicesPerkhidmatan dan BekalanRM 580,600.00RM 516,600.00RM 516,222.20
99.9%
RM 377.80JANM 2019, p. 109
050300Program Konservasi Antarabangsa Giant PandaRevised RM 6.66 mSpent RM 6.66 m
100.0%

Activity total as printed: revised RM 6,662,160.00, spent RM 6,662,159.06 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
20000Supplies and ServicesPerkhidmatan dan BekalanRM 960,400.00RM 0.00RM 0.00
0.0%
RM 0.00JANM 2019, p. 109
40000Grants and Fixed ChargesPemberian dan Kenaan Bayaran TetapRM 6,413,600.00RM 6,662,160.00RM 6,662,159.06
100.0%
RM 0.94JANM 2019, p. 109
050400Sistem e-Tanah Wilayah Persekutuan Kuala Lumpur PengurusanRevised RM 12.96 mSpent RM 12.96 m
100.0%

Activity total as printed: revised RM 12,955,300.00, spent RM 12,955,299.35 (JANM 2019, p. 109).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
20000Supplies and ServicesPerkhidmatan dan BekalanRM 12,955,300.00RM 12,955,300.00RM 12,955,299.35
100.0%
RM 0.65JANM 2019, p. 109
050500Cukai Tanah PersekutuanRevised RM 196.35 mSpent RM 234.32 m
119.3%

Activity total as printed: revised RM 196,350,000.00, spent RM 234,320,457.63 (JANM 2019, p. 110).

CodeKodSpending categoryMaksud PerbelanjaanOriginal budgetAsalRevised budgetJumlahSpentSebenar% usedPrestasiUnspentVarianSourceSumber
50000Other ExpendituresPerbelanjaan-perbelanjaan LainRM 196,350,000.00RM 196,350,000.00RM 234,320,457.63
119.3%
-RM 37,970,457.63JANM 2019, p. 110

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Operating Expenditure (Lampiran 1). % used and unspent are worked out from the printed columns.