Skip to content

Kementerian Tenaga dan Sumber Asli

A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2020, from the audited Statement of Development Expenditure.

The same code is printed as Kementerian Sumber Asli dan Alam Sekitar in 2016–2017, Kementerian Air, Tanah dan Sumber Asli in 2018–2019, Kementerian Sumber Asli, Alam Sekitar dan Perubahan Iklim in 2023 and Kementerian Sumber Asli dan Kelestarian Alam in 2024–2025.

All development votes in 2020 · Operating vote B.23 · P.23 in Budget 2027

Estimate 2020Anggaran
RM 984.69 m
Spent 2020Sebenar
RM 952.45 m
96.7% of the estimate; RM 102.96 m loan-funded
Total cost of projectsKos Keseluruhan
RM 54.75 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 11.62 bn
Totals as printed, JANM 2020, pp. 206–207

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
Jabatan Ketua Pengarah Tanah dan Galian (JKPTG)RM 2.70 mRM 2.61 m
96.6%
RM 49.79 mJANM 2020, pp. 202–203
Jabatan Ukur dan Pemetaan Malaysia (JUPEM)RM 119.78 mRM 117.62 m
98.2%
RM 509.32 mJANM 2020, pp. 202–203
Institut Penyelidikan Perhutanan Malaysia (FRIM)RM 27.42 mRM 27.42 m
100.0%
RM 122.48 mJANM 2020, pp. 204–205
Jabatan Perhutanan Semenanjung Malaysia (JPSM)RM 44.42 mRM 40.93 m
92.1%
RM 140.17 mJANM 2020, pp. 204–205
Perhutanan SarawakRM 9.90 mRM 5.46 m
55.1%
RM 60.89 mJANM 2020, pp. 204–205
Perhutanan SabahRM 24.44 mRM 22.86 m
93.5%
RM 79.99 mJANM 2020, pp. 204–205
Jumlah Perhutanan Semenanjung, Sarawak dan Sabahsums Jabatan Perhutanan Semenanjung Malaysia (JPSM), Perhutanan Sarawak, Perhutanan SabahRM 78.76 mRM 69.24 m
87.9%
RM 281.05 mJANM 2020, pp. 204–205
Jabatan Mineral dan Geosains (JMG)RM 46.12 mRM 44.57 m
96.6%
RM 206.12 mJANM 2020, pp. 204–205
Jabatan Pengairan dan Saliran (JPS)RM 159.93 mRM 159.20 m
99.5%
RM 4.02 bnJANM 2020, pp. 204–205
Bekalan AirRM 13.11 mRM 13.11 m
100.0%
RM 1.80 bnJANM 2020, pp. 206–207

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Jabatan Ketua Pengarah Tanah dan Galian (JKPTG)4 projectsEstimate RM 2.70 m · Spent RM 2.61 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
02301Projek e-TanahRM 185,882,363.00RM 0.00RM 0.00RM 25,351,190.93JANM 2020, pp. 202–203
02302Sistem e-JKPTGRM 77,017,768.00RM 2,700,361.00RM 2,608,220.10
96.6%
RM 23,618,334.27JANM 2020, pp. 202–203
02303Rekabentuk Piawaian PejabatRM 55,883,876.00RM 0.00RM 0.00RM 132,870.72JANM 2020, pp. 202–203
02304Bayaran Khas Pengambilan Balik TanahRM 800,638,000.00RM 0.00RM 0.00RM 689,958.00JANM 2020, pp. 202–203
Jabatan Ukur dan Pemetaan Malaysia (JUPEM)7 projectsEstimate RM 119.78 m · Spent RM 117.62 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
02701Sistem Pangkalan Data Geodetik (SPDG)RM 52,000,000.00RM 24,468,300.00RM 24,468,258.00
100.0%
RM 47,472,631.37JANM 2020, pp. 202–203
02703PemetaanRM 223,700,000.00RM 42,195,090.00RM 42,194,259.22
100.0%
RM 169,089,331.23JANM 2020, pp. 202–203
02801Projek Penandaan, Pengukuran dan Penyenggaraan Sempadan AntarabangsaRM 22,300,000.00RM 4,220,000.00RM 4,218,798.07
100.0%
RM 22,210,752.47JANM 2020, pp. 202–203
02803Pewujudan Sistem Pemetaan UtilitiRM 34,000,000.00RM 6,842,380.00RM 5,212,406.05
76.2%
RM 15,490,435.01JANM 2020, pp. 202–203
02804eKADASTERRM 230,253,600.00RM 19,725,560.00RM 19,725,407.01
100.0%
RM 135,293,146.02JANM 2020, pp. 202–203
02806Peningkatan Local Area Network (LAN) & Wide Area Network (WAN) JUPEMRM 32,400,000.00RM 9,637,260.00RM 9,108,231.50
94.5%
RM 23,986,634.39JANM 2020, pp. 202–203
02811Pembangunan Sistem Bahagian Geospatial Pertahanan (BGSP)RM 100,854,000.00RM 12,689,390.00RM 12,689,312.48
100.0%
RM 95,781,858.90JANM 2020, pp. 202–203
Projects printed without a group subtotal4 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
03302Kemudahan Pengurusan Kementerian (BTM)RM 455,217,504.00RM 33,732,555.00RM 33,732,449.52
100.0%
RM 102,824,583.26JANM 2020, pp. 204–205
03303Pembinaan Institut Latihan Tanah, Ukur dan Pemetaan Negara (INSTUN)RM 44,478,000.00RM 7,022,695.00RM 6,718,559.01
95.7%
RM 23,427,055.08JANM 2020, pp. 204–205
03304Infrastruktur Data Geospatial Negara (MaCGDI)RM 65,670,000.00RM 2,950,666.00RM 2,950,664.81
100.0%
RM 27,605,407.80JANM 2020, pp. 204–205
07100PERHILITANRM 345,681,673.00RM 28,863,550.00RM 28,628,937.35
99.2%
RM 159,067,283.76JANM 2020, pp. 204–205
Institut Penyelidikan Perhutanan Malaysia (FRIM)2 projectsEstimate RM 27.42 m · Spent RM 27.42 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
08100Pusat Pembangunan Produk HerbaRM 4,500,000.00RM 200,000.00RM 200,000.00
100.0%
RM 4,236,405.00JANM 2020, pp. 204–205
08510Pembangunan Penyelidikan Sumber, Pengurusan dan HasilRM 152,395,000.00RM 27,223,150.00RM 27,223,150.00
100.0%
RM 118,244,745.00JANM 2020, pp. 204–205
Jabatan Perhutanan Semenanjung Malaysia (JPSM)3 projectsEstimate RM 44.42 m · Spent RM 40.93 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
08600Pengurusan Hutan Secara Berkekalan (JPSM)RM 291,721,630.00RM 39,456,391.00RM 36,024,402.76
91.3%
RM 114,171,621.99JANM 2020, pp. 204–205
08601Penanaman Pokok Bakau dan Spesis-spesis Yang Sesuai di Persisiran Pantai (JPSM)RM 14,200,000.00RM 1,970,000.00RM 1,905,364.75
96.7%
RM 12,900,796.49JANM 2020, pp. 204–205
09200Pengembangan Maklumat Perhutanan dan IT dan K-Perhutanan (JPSM)RM 13,700,000.00RM 2,995,750.00RM 2,995,671.20
100.0%
RM 13,098,648.12JANM 2020, pp. 204–205
Perhutanan Sarawak2 projectsEstimate RM 9.90 m · Spent RM 5.46 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
09900Projek Kemajuan Perusahaan Hutan Sistem Maklumat Bersepadu Perhutanan SarawakRM 77,381,763.92RM 9,847,000.00RM 5,405,955.16
54.9%
RM 59,547,292.30JANM 2020, pp. 204–205
10100Pemuliharaan Hidupan Liar dan Projek Kerjasama Antarabangsa PerhutananRM 8,000,000.00RM 50,000.00RM 49,960.00
99.9%
RM 1,339,272.87JANM 2020, pp. 204–205
Perhutanan Sabah6 projectsEstimate RM 24.44 m · Spent RM 22.86 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
10200Penubuhan Stesen Hutan Sejadi Sabah Pusat Perhutanan Bersepadu Wilayah K.KinabaluRM 8,000,000.00RM 3,500,000.00RM 3,499,317.91
100.0%
RM 6,680,972.69JANM 2020, pp. 204–205
10300Pembangunan Teknologi Penggunaan Kayu Latihan Pencegahan Kebakaran HutanRM 9,516,850.00RM 1,155,000.00RM 1,154,997.49
100.0%
RM 8,163,478.74JANM 2020, pp. 204–205
10400Perancangan dan Pengurusan HutanRM 18,806,917.00RM 2,638,000.00RM 2,320,358.40
88.0%
RM 5,571,617.32JANM 2020, pp. 204–205
10800Pembangunan Kawasan Penyelidikan Hutan Paya Gambut Klias Galeri Perhutanan dan Penubuhan Seed Orchard serta Spesis TempatanRM 4,224,000.00RM 1,196,000.00RM 472,237.30
39.5%
RM 3,097,655.69JANM 2020, pp. 204–205
10803Program Pembangunan Mampan Sumber Hutan SabahRM 34,920,608.00RM 11,466,100.00RM 11,119,382.17
97.0%
RM 27,988,428.56JANM 2020, pp. 204–205
10804Projek Heart of Borneo (HOB) Negeri SabahRM 41,567,000.00RM 4,483,000.00RM 4,291,635.59
95.7%
RM 28,487,821.12JANM 2020, pp. 204–205
Jabatan Mineral dan Geosains (JMG)9 projectsEstimate RM 46.12 m · Spent RM 44.57 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
10900Mineral Perindustrian Semenanjung MalaysiaRM 74,200,000.00RM 8,650,000.00RM 8,269,349.81
95.6%
RM 67,279,854.67JANM 2020, pp. 204–205
11000Kajian Geologi MarinRM 5,000,000.00RM 4,130,000.00RM 4,068,094.74
98.5%
RM 4,574,575.82JANM 2020, pp. 204–205
11700Sistem Maklumat MineralRM 1,000,000.00RM 500,000.00RM 497,537.20
99.5%
RM 497,537.20JANM 2020, pp. 204–205
11800Kajian Geobencana NegaraRM 12,000,000.00RM 2,000,000.00RM 1,921,997.85
96.1%
RM 11,536,681.59JANM 2020, pp. 204–205
11900Kajian Sumber Air Tanah NegaraRM 113,500,000.00RM 20,061,500.00RM 19,476,705.81
97.1%
RM 74,402,413.15JANM 2020, pp. 204–205
12100Pembinaan Pejabat Negeri Jabatan Mineral dan GeosainsRM 44,500,000.00RM 256,377.00RM 256,356.15
100.0%
RM 329,951.15JANM 2020, pp. 204–205
12300Pemulihan Tanah Bekas Lombong dan KuariRM 5,500,000.00RM 2,850,000.00RM 2,562,337.33
89.9%
RM 4,504,675.66JANM 2020, pp. 204–205
12500Pemetaan Geologi NegaraRM 79,090,000.00RM 6,404,000.00RM 6,319,405.38
98.7%
RM 39,033,385.35JANM 2020, pp. 204–205
12600Peningkatan Taraf dan Kemudahan Makmal Jabatan Mineral dan GeosainsRM 27,900,000.00RM 1,270,000.00RM 1,195,146.08
94.1%
RM 3,960,234.19JANM 2020, pp. 204–205
Jabatan Pengairan dan Saliran (JPS)17 projectsEstimate RM 159.93 m · Spent RM 159.20 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
13200Peningkatan Inovasi dan Kemajuan TeknologiRM 44,300,000.00RM 586,700.00RM 196,630.00
33.5%
RM 17,237,146.57JANM 2020, pp. 204–205
13400Pembangunan Sumber Air NegaraRM 97,900,000.00RM 301,000.00RM 263,711.69
87.6%
RM 25,711,106.80JANM 2020, pp. 204–205
13500Pemulihan EmpanganRM 436,000,000.00RM 1,030,800.00RM 1,030,572.17
100.0%
RM 60,538,685.89JANM 2020, pp. 204–205
13600Jentera-jentera dan KelengkapanRM 54,000,000.00RM 126,700.00RM 126,650.70
100.0%
RM 41,639,634.51JANM 2020, pp. 204–205
13700Tanggungan-tanggungan untuk Pengambilan TanahRM 105,000,000.00RM 0.00RM 0.00RM 94,903,634.98JANM 2020, pp. 204–205
13900Rancangan Kawalan dan Isyarat Bahaya BanjirRM 598,000,000.00RM 3,685,900.00RM 3,485,107.33
94.5%
RM 110,581,350.22JANM 2020, pp. 204–205
14100Bangunan dan Pejabat JPSRM 6,800,000.00RM 0.00RM 0.00RM 5,623,265.05JANM 2020, pp. 204–205
14200Pemulihan StrukturRM 45,920,000.00RM 11,200.00RM 11,174.00
99.8%
RM 17,739,554.08JANM 2020, pp. 204–205
14500Menaiktaraf Infrastruktur dan Saliran Bandar, Tebatan BanjirRM 137,140,000.00RM 788,500.00RM 788,408.74
100.0%
RM 40,440,627.84JANM 2020, pp. 204–205
14600Kajian Pra KemungkinanRM 0.00RM 0.00RM 0.00RM 0.00JANM 2020, pp. 204–205
15000Kerja-kerja Kecil JPS, Pelbagai NegeriRM 150,000,000.00RM 4,300.00RM 4,239.20
98.6%
RM 121,638,113.83JANM 2020, pp. 204–205
15100Mencegah Hakisan PantaiRM 875,615,985.00RM 736,300.00RM 731,965.72
99.4%
RM 114,795,478.44JANM 2020, pp. 204–205
15200Memperbaiki, Mengindah, Membersih dan Merawat Air Sungai-sungai dan Infrastruktur MASMARM 659,680,000.00RM 5,830,800.00RM 5,830,320.64
100.0%
RM 112,260,689.22JANM 2020, pp. 204–205
15300Mengorek Kuala-kuala SungaiRM 2,332,272,906.00RM 17,383,000.00RM 17,382,428.79
100.0%
RM 1,037,697,151.93JANM 2020, pp. 204–205
15400Rancangan Pengurusan Sungai Saliran Mesra AlamRM 1,225,928,365.00RM 3,394,200.00RM 3,382,559.50
99.7%
RM 387,367,147.80JANM 2020, pp. 204–205
16700Rancangan Tebatan Banjir (RTB) dan Saliran BandarRM 10,111,282,125.00RM 124,660,900.00RM 124,577,820.19
99.9%
RM 1,822,786,808.72JANM 2020, pp. 204–205
16900Penyelidikan dan PembangunanRM 63,000,000.00RM 1,385,700.00RM 1,385,614.54
100.0%
RM 11,554,843.15JANM 2020, pp. 204–205
Projects printed without a group subtotal4 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
17000NAHRIMRM 95,544,555.16RM 2,262,600.00RM 721,278.59
31.9%
RM 60,924,673.63JANM 2020, pp. 206–207
17200Bahagian Pengurusan Biodiversiti dan PerhutananRM 75,514,000.00RM 6,990,127.00RM 5,348,068.86
76.5%
RM 44,719,851.27JANM 2020, pp. 206–207
17300Bahagian Mineral dan GeosainsRM 1,350,000.00RM 175,000.00RM 7,920.00
4.5%
RM 840,926.90JANM 2020, pp. 206–207
17500Pasukan Teras Biokeselamatan (PTB)RM 3,790,000.00RM 33,300.00RM 20,000.00
60.1%
RM 2,869,699.04JANM 2020, pp. 206–207
Bekalan Air16 projectsEstimate RM 13.11 m · Spent RM 13.11 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
06400Rancangan Bekalan Air Negeri JohorRM 787,500,000.00RM 0.00RM 0.00RM 107,821,580.58JANM 2020, pp. 206–207
06500Rancangan Bekalan Air Negeri KedahRM 1,693,665,732.00RM 0.00RM 0.00RM 152,847,401.54JANM 2020, pp. 206–207
07400Rancangan Bekalan Air Negeri MelakaRM 514,000,000.00RM 596,600.00RM 596,534.82
100.0%
RM 77,348,188.62JANM 2020, pp. 206–207
09400Rancangan Bekalan Air Negeri TerengganuNote: P.23 – Butiran 09400 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2021 telah dimasuk kira sebagai pendahuluan. 6. Teks Lampiran 2020.indd 206 6. Teks Lampiran 2020.indd 206 14/10/2021 9:43 PM 14/10/2021 9:43 PMRM 14,500,000.00RM 22,010.00RM 21,239.39
96.5%
RM 21,239.39JANM 2020, pp. 206–207
20000Rancangan Bekalan Air Negeri KelantanRM 254,043,141.19RM 0.00RM 0.00RM 64,490,834.65JANM 2020, pp. 206–207
21000Rancangan Bekalan Air Negeri SembilanRM 928,488,800.00RM 1,501,900.00RM 1,501,880.75
100.0%
RM 17,321,888.81JANM 2020, pp. 206–207
22000Rancangan Bekalan Air Negeri PahangRM 1,344,315,037.00RM 0.00RM 0.00RM 122,449,579.97JANM 2020, pp. 206–207
23000Rancangan Bekalan Air Negeri PerakRM 6,000,000.00RM 0.00RM 0.00RM 4,409.60JANM 2020, pp. 206–207
24000Rancangan Bekalan Air Negeri SelangorRM 465,797,981.00RM 0.00RM 0.00RM 182,978,534.50JANM 2020, pp. 206–207
25000Rancangan Bekalan Air Negeri TerengganuRM 45,000,000.00RM 0.00RM 0.00RM 0.00JANM 2020, pp. 206–207
26000Rancangan Bekalan Air Negeri Pulau PinangRM 1,432,700,000.00RM 14,100.00RM 14,079.81
99.9%
RM 190,957,012.68JANM 2020, pp. 206–207
27000Rancangan Bekalan Air LabuanRM 361,000,159.00RM 1,767,300.00RM 1,767,290.85
100.0%
RM 51,562,684.85JANM 2020, pp. 206–207
28000Rancangan Bekalan Air SabahRM 2,974,595,653.00RM 6,457,500.00RM 6,457,413.44
100.0%
RM 256,561,897.03JANM 2020, pp. 206–207
29000Rancangan Bekalan Air SarawakRM 2,214,137,482.49RM 541,100.00RM 541,092.00
100.0%
RM 232,245,693.00JANM 2020, pp. 206–207
30000Penyaluran Air Antara NegeriRM 3,935,575,000.00RM 1,776,900.00RM 1,776,830.79
100.0%
RM 335,169,125.27JANM 2020, pp. 206–207
31000Rancangan Bekalan Air Negeri PerlisRM 146,744,658.00RM 435,500.00RM 435,469.25
100.0%
RM 4,535,469.25JANM 2020, pp. 206–207
Projects printed without a group subtotal6 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
40000Program Kecekapan Tenaga dan Tenaga DiperbaharuiRM 148,461,000.00RM 27,247,700.00RM 27,013,491.18
99.1%
RM 27,013,491.18JANM 2020, pp. 206–207
41000Sabah Electricity Sdn. Bhd. (SESB)RM 3,695,432,577.00RM 140,369,825.00RM 126,320,479.89
90.0%
RM 126,320,479.89JANM 2020, pp. 206–207
80000Projek Pembentungan NegaraRM 10,631,438,916.66RM 279,113,090.00RM 279,112,819.29
100.0%
RM 4,030,486,478.60JANM 2020, pp. 206–207
95000NRW NASIONALRM 1,907,271,117.76RM 2,180,500.00RM 2,180,498.76
100.0%
RM 23,189,173.39JANM 2020, pp. 206–207
96000Bahagian Bekalan AirRM 63,000,000.00RM 311,800.00RM 311,779.73
100.0%
RM 1,057,322.86JANM 2020, pp. 206–207
97000PPP/PFI - Sewaan BangunanRM 297,604,469.00RM 5,615,200.00RM 5,615,178.66
100.0%
RM 5,615,178.66JANM 2020, pp. 206–207

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2020, Statement of Development Expenditure (Lampiran 2).