Kementerian Kerja Raya

A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2023, from the audited Statement of Development Expenditure.

Estimate 2023Anggaran
RM 6.69 bn
Spent 2023Sebenar
RM 6.61 bn
98.8% of the estimate; RM 215.00 m loan-funded
Total cost of projectsKos Keseluruhan
RM 71.36 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 16.72 bn
Totals as printed, JANM 2023, pp. 200–201

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Jalan Raya dan Jambatan SemenanjungRM 2.85 bnRM 2.80 bn
98.3%
RM 9.79 bnJANM 2023, pp. 200–201
Jalan Raya dan Jambatan SabahRM 132.14 mRM 110.15 m
83.4%
RM 359.49 mJANM 2023, pp. 200–201
Jalan Raya dan Jambatan SarawakRM 218.82 mRM 213.42 m
97.5%
RM 434.55 mJANM 2023, pp. 200–201
Jumlah Jalan Raya dan Jambatan Semenanjung, Sarawak dan Sabahsums Jalan Raya dan Jambatan Semenanjung, Jalan Raya dan Jambatan Sabah, Jalan Raya dan Jambatan SarawakRM 3.20 bnRM 3.13 bn
97.7%
RM 10.58 bnJANM 2023, pp. 200–201

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Jalan Raya dan Jambatan Semenanjung15 projectsEstimate RM 2.85 bn · Spent RM 2.80 bn
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00700Pembinaan Lain-lain Jalan Persekutuan dan JambatanNote: P.27 – Butiran 00700, 89000 dan 09260 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2024 telah dimasuk kira sebagai pendahuluanRM 382,258,522.00RM 1,500,010.00RM 1,500,000.00
100.0%
RM 11,460,546.84JANM 2023, pp. 200–201
02800Memperbaiki, Mengganti dan Menaikkan Taraf Jalan dan JambatanRM 1,360,955,330.00RM 147,700,000.00RM 134,648,884.20
91.2%
RM 329,883,805.74JANM 2023, pp. 200–201
12401Meminda dan Memperbaharui Bangunan Kerajaan PersekutuanRM 15,614,000.00RM 4,000,000.00RM 2,950,000.00
73.8%
RM 3,079,517.54JANM 2023, pp. 200–201
21000Membina Persimpangan BertingkatRM 645,301,000.00RM 5,500,000.00RM 2,706,926.54
49.2%
RM 8,421,134.55JANM 2023, pp. 200–201
30000Projek Menggantikan Jambatan Rosak/SempitRM 45,811.00RM 0.00RM 0.00RM 45,810.55JANM 2023, pp. 200–201
31000Pembinaan Jalan dan JambatanRM 2,496,416,709.00RM 154,050,000.00RM 149,513,261.43
97.1%
RM 473,878,624.97JANM 2023, pp. 200–201
41000Kajian Kemungkinan JalanRM 7,000,000.00RM 5,000,000.00RM 2,843,473.67
56.9%
RM 5,621,753.62JANM 2023, pp. 200–201
51000Pelbagai PembinaanRM 701,880,000.00RM 23,340,000.00RM 21,044,788.89
90.2%
RM 75,745,687.55JANM 2023, pp. 200–201
60000Naiktaraf Jalan Raya dan LaluanRM 3,066,019,190.00RM 176,701,000.00RM 172,207,370.24
97.5%
RM 759,293,883.51JANM 2023, pp. 200–201
61000Naiktaraf Jalan-jalanRM 14,913,204,061.01RM 1,378,779,010.00RM 1,378,778,987.76
100.0%
RM 2,692,709,777.46JANM 2023, pp. 200–201
71000Memperelok dan Membaik Pulih JalanRM 392,500,000.00RM 24,000,000.00RM 16,947,336.53
70.6%
RM 89,586,977.41JANM 2023, pp. 200–201
80000Membina Jalan-jalan BaruRM 476,459,046.00RM 10,500,000.00RM 4,226,898.76
40.3%
RM 129,848,022.65JANM 2023, pp. 200–201
81000Membina Jalan-jalan Baru (Projek Baru)Note: P.27 – Butiran 81000P - Peruntukan sebanyak RM115,000,000 akan dibentangkan dalam Sesi Parlimen 2024 telah dimasuk kira sebagai pendahuluanRM 9,098,244,968.40RM 628,948,000.00RM 628,947,786.58
100.0%
RM 1,666,107,108.39JANM 2023, pp. 200–201
89000Pengambilan Balik TanahNote: P.27 – Butiran 00700, 89000 dan 09260 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2024 telah dimasuk kira sebagai pendahuluanRM 313,460,820.00RM 16,000,000.00RM 11,940,735.36
74.6%
RM 130,574,546.41JANM 2023, pp. 200–201
90000Lain-lain PembinaanRM 5,352,130,940.00RM 274,161,000.00RM 274,160,796.11
100.0%
RM 3,412,514,415.27JANM 2023, pp. 200–201
Jalan Raya dan Jambatan Sabah7 projectsEstimate RM 132.14 m · Spent RM 110.15 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
05100Jalan-jalan Besar di SabahRM 380,000,000.00RM 3,400,000.00RM 623,950.35
18.4%
RM 41,290,544.31JANM 2023, pp. 200–201
08230Pembinaan JambatanRM 129,237,000.00RM 23,000,000.00RM 15,955,611.31
69.4%
RM 45,016,912.99JANM 2023, pp. 200–201
08250Kajian Perlindungan/Pembaikan Cerun-cerunRM 70,000,000.00RM 17,000,000.00RM 13,919,857.51
81.9%
RM 69,349,559.67JANM 2023, pp. 200–201
08260Naiktaraf dan Memulihkan JalanRM 424,433,000.00RM 57,000,000.00RM 50,832,768.14
89.2%
RM 144,461,312.13JANM 2023, pp. 200–201
08270Memulihkan JalanRM 14,971,082.00RM 0.00RM 0.00RM 2,731,429.12JANM 2023, pp. 200–201
08280Pembinaan Jalan-jalanRM 6,740,070,600.00RM 27,236,200.00RM 24,929,295.84
91.5%
RM 42,439,748.47JANM 2023, pp. 200–201
08600Naiktaraf Jalan RayaRM 26,100,000.00RM 4,500,000.00RM 3,883,655.61
86.3%
RM 14,196,060.48JANM 2023, pp. 200–201
Jalan Raya dan Jambatan Sarawak3 projectsEstimate RM 218.82 m · Spent RM 213.42 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
09230Jambatan-jambatanRM 0.00RM 0.00RM 0.00RM 0.00JANM 2023, pp. 200–201
09260Menaik Taraf Jalan-jalan (II)Note: P.27 – Butiran 00700, 89000 dan 09260 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2024 telah dimasuk kira sebagai pendahuluanRM 251,312,000.00RM 15,000,010.00RM 9,597,877.72
64.0%
RM 20,902,932.47JANM 2023, pp. 200–201
09280Membina Jalan-jalanRM 3,008,427,161.00RM 203,822,000.00RM 203,821,723.83
100.0%
RM 413,644,546.85JANM 2023, pp. 200–201
Projects printed without a group subtotal7 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
10000Private Public Partnership/Private Finance (PPP/PFI)RM 4,003,215,000.00RM 1,517,053,800.00RM 1,517,053,762.65
100.0%
RM 1,517,053,762.65JANM 2023, pp. 200–201
12201Pejabat Baru Kerajaan Persekutuan (di Luar Kuala Lumpur)RM 12,807,000.00RM 2,000,000.00RM 50,000.00
2.5%
RM 90,019.00JANM 2023, pp. 200–201
18610Komputer Kementerian Kerja RayaRM 14,500,000.00RM 3,880,000.00RM 3,800,000.00
97.9%
RM 14,167,404.00JANM 2023, pp. 200–201
18640Projek ICT Jabatan Kerja RayaRM 94,627,400.00RM 8,200,000.00RM 7,846,433.46
95.7%
RM 44,941,624.48JANM 2023, pp. 200–201
19000Penyelidikan dan Pembangunan KejuruteraanRM 601,934,200.00RM 1,517,300.00RM 224,483.60
14.8%
RM 74,350,160.91JANM 2023, pp. 200–201
19180Labuan, Pembinaan JalanRM 30,700,000.00RM 0.00RM 0.00RM 957,278.76JANM 2023, pp. 200–201
82000Lebuhraya Pan BorneoRM 16,337,000,000.00RM 1,955,000,000.00RM 1,950,724,731.63
99.8%
RM 4,488,303,662.62JANM 2023, pp. 200–201

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2023, Statement of Development Expenditure (Lampiran 2).