A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2025, from the audited Statement of Development Expenditure.

Estimate 2025Anggaran
RM 9.27 bn
Spent 2025Sebenar
RM 9.11 bn
98.3% of the estimate; RM 135.00 m loan-funded
Total cost of projectsKos Keseluruhan
RM 97.19 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 34.05 bn
Totals as printed, JANM 2025, pp. 216–217

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Jalan Raya dan Jambatan SemenanjungRM 3.90 bnRM 3.82 bn
97.9%
RM 16.83 bnJANM 2025, pp. 216–217
Jalan Raya dan Jambatan SabahRM 968.14 mRM 960.71 m
99.2%
RM 1.59 bnJANM 2025, pp. 216–217
Jalan Raya dan Jambatan SarawakRM 585.97 mRM 578.05 m
98.7%
RM 1.57 bnJANM 2025, pp. 216–217
Jumlah Jalan Raya dan Jambatan Semenanjung, Sabah dan Sarawaksums Jalan Raya dan Jambatan Semenanjung, Jalan Raya dan Jambatan Sabah, Jalan Raya dan Jambatan SarawakRM 5.45 bnRM 5.36 bn
98.2%
RM 19.99 bnJANM 2025, pp. 216–217

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Jalan Raya dan Jambatan Semenanjung16 projectsEstimate RM 3.90 bn · Spent RM 3.82 bn
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00700Pembinaan Lain-lain Jalan Persekutuan dan JambatanRM 1,139,281,304.00RM 0.00RM 0.00RM 11,460,546.84JANM 2025, pp. 216–217
02800Memperbaiki, Mengganti dan Menaikkan Taraf Jalan dan JambatanRM 1,594,025,330.00RM 187,635,000.00RM 186,845,554.88
99.6%
RM 767,884,059.01JANM 2025, pp. 216–217
12401Meminda dan Membaharui Bangunan Kerajaan Persekutuan SemenanjungRM 15,614,000.00RM 6,800,000.00RM 6,800,000.00
100.0%
RM 12,057,817.54JANM 2025, pp. 216–217
20000Membina Persimpangan Bertingkat dan JejambatRM 416,522,226.00RM 500,000.00RM 430,149.20
86.0%
RM 608,454.20JANM 2025, pp. 216–217
21000Membina Persimpangan BertingkatRM 840,988,365.00RM 1,500,000.00RM 304,255.72
20.3%
RM 8,725,390.27JANM 2025, pp. 216–217
30000Projek Menggantikan Jambatan Rosak/SempitRM 45,811.00RM 0.00RM 0.00RM 45,810.55JANM 2025, pp. 216–217
31000Pembinaan Jalan dan JambatanRM 2,869,133,153.00RM 98,204,000.00RM 71,400,420.27
72.7%
RM 646,426,168.89JANM 2025, pp. 216–217
41000Kajian Kemungkinan JalanRM 31,750,000.00RM 11,100,000.00RM 8,544,466.51
77.0%
RM 15,594,070.80JANM 2025, pp. 216–217
51000Pelbagai PembinaanRM 885,043,288.00RM 98,400,000.00RM 95,867,661.67
97.4%
RM 254,842,677.44JANM 2025, pp. 216–217
60000Naik Taraf Jalan Raya dan LaluanRM 4,421,276,088.00RM 147,703,000.00RM 139,287,760.24
94.3%
RM 1,007,804,662.58JANM 2025, pp. 216–217
61000Naik Taraf Jalan-jalanRM 23,142,925,140.00RM 2,142,581,000.00RM 2,131,852,481.77
99.5%
RM 6,418,251,928.40JANM 2025, pp. 216–217
71000Memperelok dan Membaik Pulih JalanRM 392,500,000.00RM 11,001,000.00RM 11,000,296.20
100.0%
RM 108,731,166.57JANM 2025, pp. 216–217
80000Membina Jalan-jalan BaruRM 960,751,049.00RM 2,301,000.00RM 1,839,900.00
80.0%
RM 147,314,111.49JANM 2025, pp. 216–217
81000Membina Jalan-jalan Baru (Projek Baru)Note: P.27 – Butiran 81000 - Peruntukan sebanyak RM135,000,000 akan dibentangkan dalam Sesi Parlimen 2026 telah dimasuk kira sebagai pendahuluanRM 12,030,267,567.00RM 630,381,000.00RM 629,506,767.32
99.9%
RM 2,928,578,464.49JANM 2025, pp. 216–217
89000Pengambilan Balik Tanah Untuk Projek-projek Jalan/JambatanRM 396,133,820.00RM 61,000,000.00RM 55,771,985.55
91.4%
RM 196,134,004.45JANM 2025, pp. 216–217
90000Lain-lain PembinaanRM 5,896,412,060.00RM 501,079,300.00RM 478,159,914.17
95.4%
RM 4,307,828,577.45JANM 2025, pp. 216–217
Jalan Raya dan Jambatan Sabah7 projectsEstimate RM 968.14 m · Spent RM 960.71 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
05100Jalan-jalan Besar di SabahRM 380,000,000.00RM 4,504,500.00RM 1,688,686.12
37.5%
RM 43,520,000.43JANM 2025, pp. 216–217
08230Pembinaan JambatanRM 156,237,000.00RM 10,811,000.00RM 10,793,686.64
99.8%
RM 67,790,876.77JANM 2025, pp. 216–217
08250Kajian Perlindungan/Pembaikan Cerun-cerunRM 219,090,000.00RM 4,430,000.00RM 866,589.05
19.6%
RM 71,105,627.34JANM 2025, pp. 216–217
08260Naik Taraf dan Memulihkan JalanRM 746,741,100.00RM 28,600,000.00RM 28,582,307.16
99.9%
RM 220,495,349.54JANM 2025, pp. 216–217
08270Memulihkan JalanRM 14,971,082.00RM 0.00RM 0.00RM 2,731,429.12JANM 2025, pp. 216–217
08280Pembinaan Jalan-jalanRM 7,187,364,040.00RM 919,793,200.00RM 918,775,049.70
99.9%
RM 1,168,849,728.26JANM 2025, pp. 216–217
08600Naik Taraf Jalan RayaRM 726,984,042.00RM 0.00RM 0.00RM 14,196,060.48JANM 2025, pp. 216–217
Jalan Raya dan Jambatan Sarawak2 projectsEstimate RM 585.97 m · Spent RM 578.05 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
09260Naik Taraf Jalan-jalan (II)Note: P.27 – Butiran 09260 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2026 telah dimasuk kira sebagai pendahuluanRM 1,117,739,062.00RM 7,474,442.00RM 7,474,431.62
100.0%
RM 45,247,424.84JANM 2025, pp. 216–217
09280Membina Jalan-jalanRM 3,767,287,161.00RM 578,500,000.00RM 570,579,156.38
98.6%
RM 1,528,593,145.59JANM 2025, pp. 216–217
Projects printed without a group subtotal8 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00107Pembangunan Iskandar MalaysiaRM 109,551,000.00RM 6,000,000.00RM 374,572.59
6.2%
RM 374,572.59JANM 2025, pp. 216–217
10000PPP/PFIRM 9,113,834,000.00RM 2,664,600,000.00RM 2,644,874,708.71
99.3%
RM 6,820,826,024.13JANM 2025, pp. 216–217
12201Pejabat Baru Kerajaan Persekutuan (di Luar Kuala Lumpur)RM 53,747,000.00RM 6,500,000.00RM 5,169,027.23
79.5%
RM 6,642,879.53JANM 2025, pp. 216–217
18610Komputer Kementerian Kerja RayaRM 22,500,000.00RM 4,250,000.00RM 2,513,862.00
59.1%
RM 17,242,347.60JANM 2025, pp. 216–217
18640Projek ICT Jabatan Kerja RayaRM 168,013,155.00RM 6,500,000.00RM 2,409,253.74
37.1%
RM 48,868,168.72JANM 2025, pp. 216–217
19000Penyelidikan dan Pembangunan KejuruteraanRM 701,095,120.00RM 11,320,000.00RM 7,300,692.29
64.5%
RM 81,971,276.46JANM 2025, pp. 216–217
19180Labuan, Pembinaan JalanRM 30,700,000.00RM 0.00RM 0.00RM 957,278.76JANM 2025, pp. 216–217
82000Lebuhraya Pan BorneoRM 17,643,000,000.00RM 1,114,674,868.00RM 1,094,351,866.80
98.2%
RM 7,081,737,727.06JANM 2025, pp. 216–217

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).