Kementerian Pendidikan

A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2018, from the audited Statement of Development Expenditure.

Estimate 2018Anggaran
RM 1.49 bn
Spent 2018Sebenar
RM 1.53 bn
102.4% of the estimate
Total cost of projectsKos Keseluruhan
RM 24.24 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 4.02 bn
Totals as printed, JANM 2018, pp. 238–239

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2018AnggaranSpent 2018Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00101Pendidikan Pra-sekolahRM 349,219,290.00RM 781,500.00RM 781,456.80
100.0%
RM 11,664,349.09JANM 2018, pp. 238–239
00102Rendah AkademikRM 3,100,764,026.00RM 133,167,000.00RM 132,743,282.39
99.7%
RM 340,645,053.97JANM 2018, pp. 238–239
00201Menengah AkademikRM 6,514,631,420.00RM 316,899,600.00RM 312,073,914.04
98.5%
RM 1,192,340,539.22JANM 2018, pp. 238–239
00202Sekolah SukanRM 185,102,420.00RM 4,657,600.00RM 4,603,438.88
98.8%
RM 13,361,786.98JANM 2018, pp. 238–239
00203Sekolah Menengah Berasrama PenuhRM 643,811,956.00RM 22,876,900.00RM 22,876,853.45
100.0%
RM 41,340,846.47JANM 2018, pp. 238–239
00204MatrikulasiRM 186,988,319.00RM 2,001.00RM 0.00
0.0%
RM 4,967,073.91JANM 2018, pp. 238–239
00300Pendidikan Teknik dan VokasionalRM 1,949,032,223.00RM 76,759,858.00RM 76,759,820.25
100.0%
RM 257,355,177.08JANM 2018, pp. 238–239
00700Pendidikan Guru - Maktab PerguruanRM 1,856,226,137.00RM 11,995,096.00RM 11,994,219.87
100.0%
RM 123,290,000.68JANM 2018, pp. 238–239
00800Rumah GuruRM 10,956,766.00RM 23,700.00RM 23,596.20
99.6%
RM 605,178.99JANM 2018, pp. 238–239
00900AsramaRM 150,920,445.00RM 4,330,401.00RM 4,322,921.67
99.8%
RM 6,137,209.19JANM 2018, pp. 238–239
01000Pejabat-pejabat PendidikanRM 180,154,500.00RM 5,879,800.00RM 5,845,614.79
99.4%
RM 9,287,388.80JANM 2018, pp. 238–239
01100Bantuan ModalRM 82,788,019.00RM 3,935,042.00RM 3,934,977.50
100.0%
RM 34,808,558.03JANM 2018, pp. 238–239
01300Pendidikan KhasRM 141,162,686.00RM 5,945,300.00RM 5,945,203.38
100.0%
RM 19,264,539.65JANM 2018, pp. 238–239
01700Pusat Pembangunan KurikulumRM 20,000.00RM 14,800.00RM 0.00
0.0%
RM 0.00JANM 2018, pp. 238–239
01800Bahagian Teknologi PendidikanRM 1,550,587,513.00RM 553,641,000.00RM 553,640,918.81
100.0%
RM 895,521,215.51JANM 2018, pp. 238–239
02200Dewan Bahasa dan PustakaRM 20,000,000.00RM 0.00RM 0.00RM 0.00JANM 2018, pp. 238–239
02300Institut Aminuddin BakiRM 76,124,400.00RM 100.00RM 0.00
0.0%
RM 488,055.80JANM 2018, pp. 238–239
03400Program Pembangunan SukanRM 107,277,502.00RM 4,174,700.00RM 4,174,638.31
100.0%
RM 40,363,393.81JANM 2018, pp. 238–239
03501Ubahsuai Naiktaraf RendahRM 391,733.00RM 2,537.00RM 2,536.35
100.0%
RM 7,149.07JANM 2018, pp. 238–239
03502Ubahsuai Naiktaraf Menengah AkademikRM 29,865,718.00RM 5,341,900.00RM 5,341,829.40
100.0%
RM 6,831,102.35JANM 2018, pp. 238–239
03503Ubahsuai Naiktaraf Maktab PerguruanRM 2,500,000.00RM 200.00RM 0.00
0.0%
RM 226,719.04JANM 2018, pp. 238–239
03504Ubahsuai Naiktaraf Sokongan PendidikanRM 1,069,982,086.00RM 20,742,660.00RM 20,742,595.79
100.0%
RM 104,906,912.58JANM 2018, pp. 238–239
03700Program Pembangunan Luar Bandar Sabah dan SarawakRM 3,485,121,969.00RM 67,530,499.00RM 67,530,495.81
100.0%
RM 351,432,905.18JANM 2018, pp. 238–239
03900Perolehan Tanah (Pendidikan) Pelbagai NegeriRM 466,342,622.00RM 127,997,104.00RM 169,496,024.15
132.4%
RM 367,866,928.79JANM 2018, pp. 238–239
04600Sistem Pengkomputeran SekolahRM 179,349,453.00RM 72,900.00RM 72,857.85
99.9%
RM 8,274,278.66JANM 2018, pp. 238–239
05100Perabot dan PeralatanRM 470,114,843.00RM 11,100,902.00RM 11,100,844.75
100.0%
RM 72,155,439.18JANM 2018, pp. 238–239
07000Bangunan dan Pejabat Kementerian Pendidikan Malaysia (KPM)RM 1,243,019,700.00RM 92,910,700.00RM 92,910,664.84
100.0%
RM 92,910,664.84JANM 2018, pp. 238–239
30000Asuhan Dan Didikan Awal Kanak-Kanak (EARLY CHILDHOOD CARE AND EDUCATION -ECCE)RM 168,879,155.00RM 3,857,640.00RM 3,857,639.44
100.0%
RM 3,857,639.44JANM 2018, pp. 238–239
42700Naiktaraf Bangunan-Bangunan Arkib Negara MalaysiaRM 5,820,019.00RM 5,820,088.00RM 5,820,018.64
100.0%
RM 5,820,018.64JANM 2018, pp. 238–239
43205Bangunan Arkib Negara Malaysia Cawangan PerakRM 8,794,401.00RM 8,794,400.00RM 8,794,400.00
100.0%
RM 8,794,400.00JANM 2018, pp. 238–239
44700Kajian Sektor KebudayaanRM 526,499.00RM 528,870.00RM 526,498.68
99.5%
RM 526,498.68JANM 2018, pp. 238–239
45000Pembangunan Teknologi MaklumatRM 0.00RM 40.00RM 0.00
0.0%
RM 0.00JANM 2018, pp. 238–239
50000Jabatan Perpustakaan NegaraRM 4,279,689.00RM 4,279,910.00RM 4,279,688.64
100.0%
RM 4,279,688.64JANM 2018, pp. 238–239

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2018, Statement of Development Expenditure (Lampiran 2).